A new AHU started during construction loads its coil, drain pan and final filters with site dust that does not vacuum off wet fins. Clean the casing before power-on, seal duct openings, run on temporary pre-filters, fit final filters after the final clean and record it for IQ.
The sequence of operation decides what a cleanroom does on restart, on a trip and in a power cut. QA usually meets it at OQ, when every change costs a software revision and a retest. Walk it line by line with QA and maintenance before panels are built: start order, trips, alarm delays and fail positions.
Heat tint is removed by pickling or mechanical cleaning, then passivation restores the oxide layer, and a treated part looks like an untreated one. The only proof is the record made at the time: procedure, chemical, contact time, date, operator and check. Collected during production, it means IQ starts from a complete file.
In a draw-through AHU the coil section runs under suction. A trap seal shallower than that suction, about 51 mm of water column at 500 Pa, draws air in through the drain and floods the pan. Checking seal depth, fall and access on the walk-down avoids an OQ deviation.
Score the technical envelope of a cleanroom HVAC tender and sign it off before any price is opened. Issue the scoring sheet with the tender: mandatory items pass or fail, the rest weighted, for example 40% technical depth and 20% each for documentation, delivery and service. Score every listed deviation.
Grade A must meet ISO 5, 3,520 particles of 0.5 µm or larger per cubic metre, both at rest and in operation. An FFU array is therefore judged with operators and machines in the zone: uniform unidirectional flow, leak-tested H14 filters and a smoke study run with the real interventions.
Balancing from the ceiling void means lifting panels over a clean room. Specify terminal HEPA boxes with a damper adjustable through the diffuser, a lock, an upstream aerosol port for the leak test, a pressure tapping and a seal the damper does not disturb, so the cascade is set with the ceiling shut.
The ISO 14644-3 installed leak test needs an upstream aerosol injection point, an upstream sample port and a perimeter seal the probe can reach. With a photometer, above 0.01% of upstream concentration is commonly treated as a leak. Specify terminal housings from the test backwards.
IQ verifies installed equipment against its records, so a file reconstructed after delivery delays qualification. Humiley compiles material certificates, weld and passivation records, the witnessed FAT report, O&M manual and spares list while each unit is built, so IQ starts from a complete record.