Every kW of cooling at a 6 K chilled-water difference needs about 0.14 m³/h of water, so a 500 kW plant moves about 72 m³/h.
The number comes from the heat capacity of water, 4.19 kJ/kg·K, times 6 K. It is worth carrying in your head because pipe and pump sizes follow from it directly. At 72 m³/h a DN150 main runs at about 1.1 m/s. Design the same load on a 5 K difference and the flow is 20% higher, and the pipes, valves and pump grow with it.
Operation is where the difference gets lost. The design says 6/12 °C, but coils with valves stuck open, bypasses left open after balancing and coils fouled on the air side send water back at 10 °C instead of 12. The difference falls to 4 K and the same load needs 0.22 m³/h per kW, 50% more water. On a fixed system, 50% more flow needs about 2.25 times the pressure and 3.4 times the pump power, which the pumps do not have. What usually happens is that a second chiller and pump start up to carry a load the first could have met.
So the temperature difference is a design value to protect: two-way valves at the coils, no permanent bypasses, and a return temperature trend at the plant that somebody reads.
Humiley designs for the tropical climate the plant sits in, with energy modeling that targets 30% lower HVAC energy.
Topics