A pipe route changed on site to clear a cable tray, and the IQ protocol still references the design drawing.
Annex 15 has IQ verify the installation against the engineering drawings and specifications. When site changes were never captured, that leaves two outcomes. The IQ engineer walks the line, finds the difference, and raises a deviation late in the project. Or nobody looks closely, IQ is signed, and the plant now has a qualified state described by a drawing that does not match it. The second outcome is worse, because it surfaces at the first change control or the first inspection.
Doing it the other way round means the as-built is in the turnover package before IQ starts. The installer red-lines each change, the design engineer reviews it against the design basis, and every change is either accepted into the approved documents or corrected on site. IQ then verifies the plant against drawings that are both approved and true.
Most of this is site discipline rather than paperwork: marking up changes in the week they happen, while the fitter still remembers why.
Humiley manages construction into qualification as a handover of its own, with systems turned over package by package so IQ starts from a verified installation.
Who owns the red-line drawings on your current project, the contractor or the design team?