"The filling room is held at least 10 Pa above the adjacent Grade C corridor."
That URS line reaches further into the HVAC design than it looks. At OQ it becomes a pressure differential measurement with 10 Pa as the acceptance limit, and working backwards from that test gives the engineer several decisions to make while supply and return airflows are still being chosen.
The first is leakage. The offset between supply and return has to cover what escapes through the door and any transfer grilles, estimated with the door seals as they will be after a year of use, because an offset that only holds on new gaskets will fall short later.
The pressure control loop comes next, with its normal operating band set well clear of 10 Pa so the dip when the corridor door opens does not read as a failure. The alarm goes between that band and the limit, so an operator hears about a falling differential before the room drops under what the URS promised.
Compliance is one of the values Humiley works to. At design stage it means the URS, validation strategy and qualification roadmap are written in parallel with the design, so a line like this one is on the engineer's desk before the airflows are fixed.
How early does the URS reach your design team?
Industries