16 sampling locations where there used to be 10

  • News
  • 1 min read

Under the 1999 edition of ISO 14644-1, a 100 m² cleanroom needed 10 classification sampling locations. Under the 2015 edition it needs 16.

The old rule was a square root: the number of locations was the square root of the floor area, rounded up. The 2015 revision replaced it with Table A.1, which reads the count straight from the area and climbs faster for mid-sized rooms. For 100 m² the table gives 16. Above 1,000 m² a formula takes over from the table.

Two other things changed at the same time. The 95% upper confidence limit calculation, which applied to rooms with two to nine locations, was dropped. And the room is now divided into sections of roughly equal area with one location in each, so the plan has to show where every point sits, not only how many there are.

On a running site this shows up in the requalification plan. Plans written before 2016 often still carry the old counts, and nobody notices until an auditor lays the plan beside the standard. The extra points also cost counting time: six more set-ups and sample runs on a 100 m² room, every time it is requalified.

Check the location count in your classification SOP against Table A.1 before the next requalification, not during it.

Qualification and requalification services

Related

More on this subject

Both states are required; only the stage is a choice

A 50 m² Grade B room needs 10 classification locations under ISO 14644-1:2015, and EU GMP Annex 1 requires them at rest against ISO 5 and in operation against ISO 7, with the smoke study in both states. Whether each run sits in OQ or PQ is for the URS and risk assessment to justify.

InsightRead

Environmental monitoring locations and their rationale

Classification spreads sampling points evenly by floor area; environmental monitoring should go where contamination would reach open product first. Place particle probes and settle plates from the smoke study, the intervention list and a documented risk assessment, keep them clear of the flow, cover the last-to-recover spots, and reference the evidence behind each point.

InsightRead

How to qualify a cleanroom testing contractor

Cleanroom testing is often bought late and on price, and QA first meets the tester as a signature on a report. Before the order, hold evidence of tester training, calibrated instruments, method statements to ISO 14644-1 and ISO 14644-3, a sample report and agreed raw data practice, then list the tester as an approved supplier.