ASTM E2500 is a short guide, and two of its ideas decide how much of a factory test is repeated on site.
Verification is led by subject matter experts, the people with the expertise and the responsibility for a system, whichever department they sit in. They plan the verification, define acceptance criteria and test methods, run the tests and review the results. The quality unit keeps a narrower part. As ISPE summarises the 2025 edition, it approves the verification plans and the conclusion that a system is fit for use, while commissioning test documents such as FAT and SAT do not need its pre-approval.
Vendor documentation, test records included, may be used as part of the verification evidence, provided the company has assessed the vendor: its quality system, its technical capability and its application of good engineering practice.
EU GMP Annex 15 (2015 text) leaves room for the same thing. Where appropriate and justified, documentation review and some tests could be performed at the FAT without being repeated at IQ/OQ, if it can be shown that transport and installation do not affect the functionality.
At Humiley the URS, validation strategy and qualification roadmap are written in parallel with the design.
Who verifies and whose documents count both have to be settled before the FAT, which puts them in the weeks when the URS is written.