Three PPQ batches: where the number has to come from

  • Life Sciences
  • 1 min read

A plant filing the same tablet in Europe and the US has to pick one PPQ batch count and defend it to two sets of inspectors.

EU GMP Annex 15, revised in 2015, treats three consecutive batches under routine conditions as a common minimum, with the number justified from risk. The FDA's 2011 process validation guidance never gives a figure. It splits the work into Stage 1 process design, Stage 2 process qualification and Stage 3 continued process verification, and asks whether the Stage 2 data show a capable process.

The count therefore stands or falls on the written rationale. Rationales that survive questioning usually start with commercial-scale history: how many batches exist and how far each critical quality attribute moved between them. Parameters running near the edge of their proven range add variation and push the number up. A platform process or a sister product on the same line earns some of it back. The better rationales finish with a statistical target, for example a capability index on the CQAs, and work out how many batches it takes to estimate that index with reasonable confidence. For a new sterile product with thin scale-up data, that arithmetic often lands above three.

PPQ comes after the facility's own IQ and OQ, the earlier stretch of the V-model where our commissioning and qualification work sits.

Industries

Related

More on this subject

CPV: one abbreviation, two different things

Continued process verification is the FDA's Stage 3: assurance during routine production that the process remains in a state of control. EU GMP Annex 15 (2015) calls it ongoing process verification. Continuous process verification, defined in ICH Q8(R2), is an alternative approach to validation. Write the phrase out and cite its source.

InsightRead

GEP: what qualification can rely on, and what it repeats

Good engineering practice is the design review, installation checks and commissioning that sit under qualification. WHO's HVAC guideline defines it, and EU GMP Annex 15 (2015) allows data from outside the manufacturer's own programs if justified and controlled. Commissioning sheets made with calibrated instruments and signed by the person who measured can then be relied on.

InsightRead

How to correct a GMP record

EU GMP Chapter 4 asks that any alteration is signed and dated, leaves the original readable and records a reason where appropriate. Correction fluid, overwritten digits and blacked-out entries all break that rule and ALCOA+. Engineering and site teams need it in their induction as much as QA.

InsightRead