With an IQ deviation still open, OQ can begin: EU GMP Annex 15 allows it, on a condition set out in clause 2.10 of the 2015 text.
The clause says a formal release for the next stage should be authorised by the relevant responsible personnel, either as part of the validation report approval or as a separate summary document. Conditional approval to proceed can be given where certain acceptance criteria or deviations have not been fully addressed and there is a documented assessment that there is no significant impact on the next activity.
That assessment is made item by item. Say IQ closed with the calibration certificate for the room pressure transmitter still missing: that touches every pressure test in OQ, and "no significant impact" cannot honestly be written. An operating manual still waiting for translation touches none of them.
The assessment looks at the next activity. If the item is still open when PQ is due, the release to PQ needs an assessment of its own.
The Annex stops there. Sites usually add an owner and a date for the open item, and close it before the final report is signed.