Before the AHU swap: record the room as found

  • Manufacturing & Distribution
  • 1 min read

Before the old AHU is disconnected, we take one set of readings: the room as it is today.

Airflow at each supply terminal. Pressure across every door in the cascade. Temperature and RH in each room. All recorded with the instruments that will be used after the swap.

That as-found record does two jobs. It is the target the new unit is balanced back to on Sunday night. And it is the evidence that the replacement restored the qualified state rather than creating a new one.

Skip it, and on Monday the cascade between two rooms is lower than anyone remembers. Nobody can tell whether it is the new fan, a damper someone touched during the work, or a room that had been drifting for months.

There is a second reason. The old unit is often not delivering its design airflow any more, and the rooms were qualified at what it actually delivered. Balance the new unit to design and you have changed the room. Balance it to the as-found and you may be carrying an old shortfall forward. That is a decision for QA and change control, and it is much easier on Wednesday than at 2 a.m. on Sunday.

We take on jobs from a single AHU replacement in a running facility to a full greenfield plant. The readings come first on all of them.

When you last replaced an AHU, did you balance to the design flow or to the as-found?

Related

More on this subject

Set a device assembly room's class from the product's risk

ISO 13485 §6.4.2 asks for documented contamination control without naming a cleanroom class. Setting the class from sterilisation method, patient contact and bioburden sensitivity often lands device assembly at ISO 8, with ISO 7 only where needed, less air than Grade C, a smaller AHU and a reason an auditor can read.