Skip to content

Manufacturing & Distribution

Capacity reservation vs firm order for long-lead AHUs

  • Manufacturing & Distribution
  • 1 min read

Custom AHU factory slots can go months before the airflow schedule is final. Ordering early to hold one buys a string of variations.

There is a middle step that many owners skip: a capacity reservation. The vendor holds production capacity for a stated number of units and a delivery window. The owner commits to a spec-freeze date, usually with a reservation fee or a letter of intent. The firm order follows once the design is fixed.

For an AHU, the freeze list is short and specific: airflow and external static pressure, coil duties, section arrangement and overall dimensions, EN 1886 casing classes, and the controls interface. Change one after the freeze and the vendor can move you out of the slot.

A firm order placed before those are fixed works the other way. The slot is secure, and every design change after it becomes a priced variation and a new approval cycle. On a GMP project, changes at that stage are normal, because room data sheets are still moving.

The reservation has its own exposure if the project slips: fees may not be refundable, and the slot may not wait. Read those terms before signing.

On our projects equipment is selected against the calculated loads during design, so the freeze list exists by the time a slot has to be held.

Related

More on this subject

Set a device assembly room's class from the product's risk

ISO 13485 §6.4.2 asks for documented contamination control without naming a cleanroom class. Setting the class from sterilisation method, patient contact and bioburden sensitivity often lands device assembly at ISO 8, with ISO 7 only where needed, less air than Grade C, a smaller AHU and a reason an auditor can read.

InsightRead