Of the five things a closed NCR has to show, the word most site NCRs close with, "rectified", covers one.
The five, in order:
- Record what was found and the requirement it breaks: drawing number, specification clause, location, photo. "Poor weld" cannot be closed, because nothing on the form says what a good one is.
- Contain it. Tag the item and hold the next activity that would hide it, such as insulation over a pipe joint.
- Decide the disposition and name who decided: rework, repair, use as is, or reject. Repair and use-as-is leave the item different from the drawing, so they need the designer's acceptance, and QA's on a GMP system.
- Find the cause and look for the same fault elsewhere. One welder or one drawing revision rarely produces a single defect.
- Verify against the original requirement, attach the evidence, then close.
Most of these steps are in ISO 9001, which lists correction, segregation or containment, informing the customer and acceptance under concession as ways to deal with a nonconforming output. Conformity must be verified after a correction, and the record must describe the nonconformity, the actions taken, any concession and who authorised the decision. Its corrective action requirements add the cause, and whether similar nonconformities exist or could occur. Our project management work runs on an ISO 9001-aligned QMS.
"Rectified" answers step 3 and leaves out who decided.




