A ceiling diffuser a metre from a fume hood's face can pull vapour out past the sash, whatever the factory test showed.
A hood holds vapour back by drawing room air in through the sash opening, typically at around 0.5 m/s. Air from a nearby high-throw diffuser can cross the face faster than that, and when it does it drags vapour out past the sash. A common design rule keeps cross-drafts at the hood face below half the face velocity, so about 0.25 m/s for a 0.5 m/s hood.
Most of the room layout follows from that one number. Supply outlets go away from hood faces and are chosen for low discharge velocity, so air reaches the hood slowly and from the front. Hoods sit at the far end from the door and out of the walking route, because an opening door or a person passing the sash sends a stream straight across the bench. General exhaust goes where it clears the room without competing with a hood.
A lab handling hazardous material is usually held slightly negative to the corridor, and its makeup air has to arrive without breaking the same rule.
The factory test cannot see any of this. An as-installed ASHRAE 110 or EN 14175-4 test, run in the finished room with the HVAC balanced, can.