How to qualify a cleanroom testing contractor

  • Life Sciences
  • 1 min read

Nobody on site ever assessed the company that signed the classification report in the qualification file.

Cleanroom testing is often bought late and on price. QA meets the testing company for the first time as a signature on a report it is asked to approve.

Chapter 7 of EU GMP covers any outsourced GMP activity. Under its 2013 text the contract giver is responsible for assessing the legality, suitability and competence of the contract acceptor before the work is outsourced.

QA should have on file, with the order still unsigned:

  1. Training records or tester certification for the people who will be on site, by name.
  2. The instrument list with calibration certificates in date: particle counter, photometer, anemometer or hood, micromanometer.
  3. Method statements for each test, to ISO 14644-1 for classification and ISO 14644-3 for the supporting tests.
  4. A sample report from an earlier job. ISO 14644-1 lists what it shall include, down to sampling locations, departures from the method and the instrument's calibration certificate.
  5. How raw data is recorded and corrected. Particle counter printouts and files are raw data.

Then the tester goes on the approved supplier list with a review date.

Industries

Related

More on this subject

The ISO 14644-3 recovery test times a 100:1 fall in particle concentration after an aerosol challenge and measures the air system. The Annex 1 clean-up period, under 20 minutes as a guidance value and set during qualification, describes the room after real operations. Write the recovery test into the URS and set the clean-up period at in-operation qualification.

InsightRead

WFI belongs in the Contamination Control Strategy

EU GMP Annex 1 (2022) gives WFI circulation above 70 °C as an example of minimizing the risk of microbial growth. Keeping a loop hot drives the design: ASME BPE dead legs of L/D ≤ 2, turbulent flow to the last user point, planned sanitization and sensors on the return. The CCS should justify all of it.

InsightRead

Why cleanroom airflow is called unidirectional

At 0.45 m/s across a 1 m clean zone the Reynolds number is about 30,000, far beyond laminar flow. ISO 14644-1 and the 2022 EU GMP Annex 1 use the term unidirectional airflow: steady velocity, roughly parallel streams. It is tested by air speed, uniformity and smoke studies, so write it that way in the URS.

InsightRead