IEEE 519 voltage limits: 8% at LV, 5% at 22 kV

  • News
  • 1 min read

At 400 V, IEEE 519-2022 allows 8% total voltage distortion. At 22 kV the limit drops to 5%.

Table 1 of the standard splits voltage limits by bus voltage at the point of common coupling (PCC). At 1 kV and below: 5% for any single harmonic, 8% total. Above 1 kV up to 69 kV: 3% for any single harmonic, 5% total.

Which row applies depends on where the PCC is, and that is where designs go wrong. A plant that takes its supply at 22 kV and owns its transformers has its PCC on the 22 kV side. The 400 V switchboard inside the plant is not the PCC, however many analysers are clipped onto it.

So the 3% and 5% voltage limits apply at the plant's PCC. The plant's own obligation is its TDD limit, which is its share of that budget. The stiffer MV network helps, because the same harmonic current produces less voltage distortion across a lower source impedance. But the 5th and 7th from a row of EC fan walls pass through the transformer to the MV side.

The voltage limits are the network's budget. Each customer's harmonic currents spend part of it, which is why a utility looks at what a new plant injects before it connects. Vietnam's Circular 05/2025/TT-BCT sets its own requirements on top.