In a perfectly mixed room, cutting the particle count by 100:1 takes 4.6 air changes. No real room is perfectly mixed.
The physics is dilution. With clean supply air and perfect mixing, concentration falls as C/C0 = e^(−N·t), where N is the air change rate. A 100:1 reduction needs N·t = ln(100), which is 4.6 air changes.
At 20 ACH that is 4.6/20 of an hour, about 13.8 minutes. At 40 ACH, just under 7 minutes.
Real rooms take longer. Air short-circuits from supply to return along the ceiling, corners behind equipment get little clean air, and a low return grille in the wrong place leaves a stagnant pocket at working height. The ratio between the theoretical 4.6 air changes and what you measure is a direct reading of how well the room mixes.
That gap is exactly what the recovery test in ISO 14644-3 measures: the time to reach a 100:1 reduction after the room is challenged with particles. A room that needs 25 minutes at 20 ACH is telling you something about its airflow pattern that the classification test will not.
So use the formula before the test, not instead of it. If the design ACH and a realistic mixing allowance already predict a slow recovery, move the diffusers and returns while they are still lines on a drawing.