Reheat sources, ranked by what each kWh costs

  • News
  • 1 min read

Every kWh of reheat after a dehumidifying coil is heat you paid to remove a moment earlier.

The size is easy to check. Raising air by 1 K takes about 0.34 kW per 1,000 m³/h (1.2 kg/m³ × 1.006 kJ/kg·K). Lift supply air 5 K after the coil on a 20,000 m³/h unit and the reheat load is about 34 kW, whenever the room needs dry air.

Ranked from most expensive to least per kWh delivered to the air:

  1. Electric resistance. One kWh bought, one kWh of heat. Cheap to install, dearest to run.
  2. Boiler hot water. Combustion and distribution losses mean each kWh at the coil costs more than a kWh of fuel; whether it beats resistance depends on local fuel and electricity prices.
  3. Heat pump. At a COP of 3, three kWh of heat per kWh of electricity.
  4. Condenser heat recovery. The chiller is rejecting that heat to the tower anyway. The cost is a recovery condenser, pumping and sometimes a higher condensing temperature.
  5. Wrap-around heat pipe. It pre-cools the air before the cooling coil and reheats it after, with no compressor. The cost is fan pressure drop and casing length.

Tariffs can reorder the middle; the site decides what is usable: whether the AHU has length for heat pipe coils, whether the chiller runs when reheat is needed, and whether the load is steady or only appears on wet nights.

In the tropics reheat is a primary design decision, so we count it at design stage.

Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Related

More on this subject

Manufacturing & Distribution

Where the steam humidifier sits in the AHU

Steam that has not absorbed before it meets a filter, fan or sensor leaves them wet. Take the absorption distance from the maker at the unit's real air speed and load, keep wet-sensitive parts beyond it, fit a trapped stainless drain pan and access, and add a downstream high-limit sensor.

InsightRead