An RFI emailed on a Tuesday afternoon waits in the design office queue, and the ceiling crew waits or guesses with it.
On a GMP project most site questions are small. A duct meets a beam 80 mm lower than the model showed. A damper has no access from the corridor side. A sprinkler branch needs a new route. The contractor sketches a fix, and someone with design authority has to accept it before it is built.
A designer's engineer resident on site can accept it the same morning, marked up on the drawing where the work is. The emailed route, where the sketch joins a log and gets checked against the model between other jobs, is cheaper and leaves a cleaner paper trail. It also takes days, and in a congested ceiling void six trades end up waiting on each other.
Paying for a resident engineer swaps idle crews for a monthly fee, and it adds one document the owner should not skip: a written list of what that engineer may sign. Anything touching airflow, the pressure cascade or a room class should still go back to the design lead, or the as-built drifts away from the design basis.
In our view resident cover pays for itself during the months of dense MEP installation and not much outside them. For the rest of the job, a tracked RFI log with an agreed turnaround does the work.
Industries




