Analytical method transfer comes before the first batch

  • News
  • 1 min read

A receiving site cannot test its first batch with a method it has only read.

The step in between is analytical method transfer. USP <1224> describes it as the documented process that qualifies a laboratory, the receiving unit, to use an analytical test procedure that originated in another laboratory. What has to be shown is that these analysts, on these instruments, get the result the method's owner would get.

The chapter lists four routes: comparative testing of the same samples in both laboratories, co-validation, revalidation in full or in part, and a waiver where it can be justified. The WHO guideline on technology transfer (TRS 1044, Annex 4) says the strategy chosen should be risk based and scientifically justifiable.

The same guideline sets the order of work. Analytical procedures should be implemented at the testing laboratory before samples for process validation studies are tested by the receiving unit, and the receiving unit should formally agree on acceptance criteria before the transfer protocol is executed. Criteria written after the numbers are in tend to fit the numbers.

On a project plan this puts the laboratory ahead of production, with instruments qualified, analysts trained and the protocol signed before the first validation batch is made.

On your transfer schedule, does the QC laboratory start before production or after it?

Industries

Related

More on this subject

Annex 11 and the BMS-to-EMS link

The 2011 text of Annex 11 (clause 5) says systems that exchange data electronically should include built-in checks for correct and secure entry and processing. On a BMS-to-EMS link we read that as status flags, a communication watchdog, end-to-end checks of units and time stamps, and a loss-of-communication test in the qualification.

InsightRead

Annex 11 supplier assessment belongs in the validation plan

EU GMP Annex 11 clause 3.2 makes supplier competence and reliability part of computerized system validation, with the need for an audit set by risk. For SCADA, BMS and EMS, supplier records can reduce the testing the user repeats; the URS, risk assessment and configuration tests such as alarm limits and user roles stay with the user.

InsightRead

Annex 15 and the open deviation between qualification stages

EU GMP Annex 15 (2015) says a formal release for the next qualification stage should be authorised, and that conditional approval to proceed can be given where there is a documented assessment of no significant impact on the next activity. That assessment is made item by item, against the tests that follow.

InsightRead