Tender what the design already selected

  • Engineering Solution & Consultancy
  • 1 min read

A tender line that says "AHU to suit" gets priced by whichever bidder is least careful about what "to suit" means.

When the bidder selects the equipment after issue, the decisions that set the price are made under price pressure. Coil rows, fan working point, casing class to EN 1886, filter stages. Six bids come back with six different units inside them. Comparing them is guesswork, clarifications run past award, and the gaps return later as variations.

When the design team selects against the calculated loads, those decisions are made once, with the load calculation open on the desk. The coil is checked at wet-season design conditions. The fan is checked at the real system pressure. The tender then describes something that is known to be buildable, and the cost plan was priced on that same selection.

It costs design hours, and owners sometimes worry it locks them to one vendor. It does not have to. Write the requirement as performance plus a reference selection, and accept equals that meet the same tested performance.

Design into procurement is the first of the four handovers we manage on a project, because it is where the budget is either confirmed or quietly lost.

If this sounds like your last tender, talk to one of our engineers: contact@humiley.com or +84 28 7777 6668 (Viet Nam office).