WFI without a still: what changed in 2017

  • Life Sciences
  • 1 min read

Since April 2017, Ph. Eur. monograph 0169 has allowed Water for Injections to be produced without distillation.

What changed is the generator. The specification stayed where it was, bacterial endotoxin still below 0.25 IU/mL, and the storage and distribution loop can still be kept hot whichever way the water was made.

A multi-effect still boils its feed, so the generator itself runs at temperatures where biofilm cannot settle. It pays in steam and cooling water for the life of the plant. An RO-based train runs at ambient temperature on far less energy, but its membranes, pretreatment and the pipework between them sit in the range where bacteria grow. That part needs its own controls: hot-water or chemical sanitization, a membrane integrity check, and online TOC, conductivity and microbial sample points ahead of the loop.

The EMA Q&A on non-distillation WFI deals mostly with those questions, and the answers fix valves and sample points, so they come before the P&ID.

Feed water counts on both routes, because a still needs pretreated feed too. With membranes it counts for more, since nothing in the generator runs hot. Where a municipal supply in Viet Nam changes hardness, silica or organics with the season, pretreatment sizing needs samples from the wet and the dry months.

PW, WFI and Pure Steam are in our engineering scope. On your last WFI project, what settled the choice?

Industries

Related

More on this subject

Engineering's part of the product quality review

The 2013 text of EU GMP Chapter 1 lists the qualification status of relevant equipment and utilities among the items a product quality review should include. Engineering can make that line believable with four more inputs: changes in the period, excursions and trends, calibration and maintenance failures with product impact, and the status of engineering CAPAs.

InsightRead

Four checks at the basic-design gate

Before detail design opens, a GMP project should have frozen room data sheets and pressure cascade, loads that match the equipment list, a URS for each critical system and owned open items. A cascade change after the ducts are drawn reaches the duct sizes, terminal filters, AHU selection and every neighbouring pressure step.

InsightRead