Since April 2017, Ph. Eur. monograph 0169 has allowed Water for Injections to be produced without distillation.
What changed is the generator. The specification stayed where it was, bacterial endotoxin still below 0.25 IU/mL, and the storage and distribution loop can still be kept hot whichever way the water was made.
A multi-effect still boils its feed, so the generator itself runs at temperatures where biofilm cannot settle. It pays in steam and cooling water for the life of the plant. An RO-based train runs at ambient temperature on far less energy, but its membranes, pretreatment and the pipework between them sit in the range where bacteria grow. That part needs its own controls: hot-water or chemical sanitization, a membrane integrity check, and online TOC, conductivity and microbial sample points ahead of the loop.
The EMA Q&A on non-distillation WFI deals mostly with those questions, and the answers fix valves and sample points, so they come before the P&ID.
Feed water counts on both routes, because a still needs pretreated feed too. With membranes it counts for more, since nothing in the generator runs hot. Where a municipal supply in Viet Nam changes hardness, silica or organics with the season, pretreatment sizing needs samples from the wet and the dry months.
PW, WFI and Pure Steam are in our engineering scope. On your last WFI project, what settled the choice?