What the site supplies to the Manufacture section of a dossier

  • Life Sciences
  • 1 min read

Regulatory affairs assembles the dossier, but one section of Module 3 is written almost entirely from what the site knows.

In ICH M4Q(R1) it is section 3.2.P.3, Manufacture, with five sub-sections. The site's inputs for each:

  1. Manufacturers. The name, address and responsibility of each manufacturer, contractors included, and of each site involved in manufacturing and testing.
  2. Batch formula. All components, their amounts per batch including overages, and a reference to their quality standards. It comes from the master formula.
  3. Process description and controls. A flow diagram showing where materials enter and where controls sit, and a narrative that includes packaging. The guideline says equipment should at least be identified by type and working capacity, where relevant.
  4. Controls of critical steps and intermediates. Tests and acceptance criteria at the critical steps, with justification. The in-process control sheets on the floor should say the same.
  5. Process validation or evaluation. Description, documentation and results of the studies for the critical steps.

What each region wants under these headings differs, and regulatory affairs decides that. Humiley's EU-GMP roadmap consulting covers the CTD/eCTD dossier, with QMS and technology transfer.

The site's job is inputs that agree with each other and with the floor.

Industries

Related

More on this subject

Campaign length belongs in the cleaning validation

Batches of one product run back to back leave more baked-on product, packed fines and microbial growth for the final clean. The 2015 text of EU GMP Annex 15 (clause 10.9) says the maximum length of a campaign, in time and/or number of batches, should be the basis for cleaning validation. Set that maximum and validate after it.

InsightRead

Five points of EU GMP Annex 15 (2015) shape a cleaning validation protocol: all product contact equipment, residue limits based on a toxicological evaluation, dirty and clean hold times, dedicated equipment or other appropriate measures where cleaning is ineffective, and manual cleaning confirmed at a justified frequency. All five are written with 'should'.

InsightRead