Once the last ceiling panel is in, everything above it becomes hard to check.
A panel ceiling hides the ductwork, the pipework and most of what goes wrong in the first wet season. Looking above it is easy only for a short window in the program. Before close-up we would want these signed off for each area:
- Supports and hangers complete. Every hanger loaded, no duct resting on the ceiling grid, no temporary wire.
- Insulation and vapour seal continuous. Look at hangers, valves and flanges, where the vapour barrier gets cut and is not taped back. In this climate a gap becomes a drip on the panel below.
- Dampers and valves reachable and tagged. Stand at the access panel and try to reach the actuator. The tag matches the drawing.
- Penetrations sealed. Each duct, pipe and cable crossing a wall or slab is closed with the specified seal, including the ones nobody can see from the room.
- Test ports fitted, and nothing left behind. Offcuts, cable ties and dust above a cleanroom ceiling stay there.
Photograph each bay with its grid reference. Later the photos are the only view anyone gets, and they belong with the inspection record in the handover package.
On our projects, systems are commissioned, balanced and turned over package by package, so IQ starts from a verified installation instead of an open punch list.