Each OQ result, all of them within limits, carries a date four days earlier than the approval signature on the protocol.
That order means the acceptance criteria may have been written with the results already known. The tests may be sound, but the record can no longer show it.
EU GMP Annex 15 (2015) has no sentence that says "approve before you test". The text gets there in two steps: significant changes to the approved protocol during execution should be documented as a deviation, and results that fail the pre-defined acceptance criteria should be recorded as a deviation. "Approved" and "pre-defined" mean something only if the signature comes first. It also says the work should only be performed by suitably trained personnel, so the testers' training records need an earlier date too.
The usual cause is the calendar: the vendor's engineer leaves on Friday.
The annex leaves a route for earlier work: data obtained outside the manufacturer's own program may be used, provided the approach has been justified and there is adequate assurance that controls were in place while the data were acquired. Put that justification in the plan beforehand.
If the dates are already wrong, leave them as they are. Raise a deviation, assess what the early tests can still support, and repeat the rest under the approved protocol.