Where the pump's differential pressure sensor belongs

  • News
  • 1 min read

A chilled-water pump on a drive that holds design head across its own headers runs close to full speed all night.

Its sensor is piped across the headers, two metres from the pump. The loop holds full head at every flow, and the control valves out in the building throttle away the pressure the pump has just made.

Say the design head is 300 kPa: 60 kPa for the index coil and its valve, 240 kPa of pipe friction. At half flow the friction falls to a quarter, 60 kPa. With the sensor holding 60 kPa at the index coil, the pump head can drop to 120 kPa. The sensor at the pump still asks for 300: two and a half times the head for the same flow.

In ASHRAE 90.1, a US energy standard, differential pressure in a variable-flow hydronic system shall be measured at or near the most remote heat exchanger, or the one requiring the greatest differential pressure. With DDC, the setpoint shall be reset downward from valve positions until one valve is nearly wide open. Local codes and the contract decide whether it applies in Viet Nam.

The sensor lands at the pump because the cable run is short, the remote coil is in another package and no drawing puts it elsewhere. Name the index circuit in the hydraulic calculation and draw the transmitter there. Where that cable is hard to run, resetting from valve positions gets most of the way. It needs every valve position on the BMS, and one stuck valve can then hold the pump at speed.

Related

More on this subject

Zero growth and the HVAC record around a media fill

Annex 1 sets zero growth as the APS target, and any contaminated unit fails it. The environmental side of the investigation starts from viable monitoring, with HVAC and EMS trends as support, so review trends before the fill, confirm logging and clock sync, and agree which HVAC events count as interruptions.

InsightRead

ALCOA+ on a paper pressure log

A paper room-pressure log with every reading in the same pen at the end of the shift fails ALCOA+ before any number is checked. Walking one sheet against the nine attributes, from attributable initials to enduring ink, shows that most data-integrity failures are fixed by redesigning the form.

InsightRead