Duct leakage, cascade balance, controls tuning and recovery can only be measured once an AHU is connected on site. A FAT can still speed up those tests by recording clean filter and coil pressure drops, the casing leakage result, fan airflow at design static and the panel software version with its I/O list.
A 900 mm cleanroom door with a 5 mm undercut leaks about 50 m³/h at 15 Pa, and about 100 m³/h at 10 mm. Door gaps set how much offset air holds a 10–15 Pa cascade. Specify door leakage as a number at a stated pressure, with the test, and check it before installation.
Late service penetrations through cleanroom panels are a common reason a room loses its pressure differential. Sleeve each one to the panel, seal both faces with a flush cover on the clean side, run one service per sleeve and keep a penetration schedule that is checked before the pressure test.
An old AHU leaves with loaded filters, a wet drain pan and shedding insulation. Plan the crane lift or sectional removal route, bag filters and blank ducts before it moves, hold the plant room negative while casing is cut, and watch the neighbouring suites' pressure differentials.
Balancing from the ceiling void means lifting panels over a clean room. Specify terminal HEPA boxes with a damper adjustable through the diffuser, a lock, an upstream aerosol port for the leak test, a pressure tapping and a seal the damper does not disturb, so the cascade is set with the ceiling shut.
IEC 61439-2 defines four forms of internal separation in a switchboard. Form 4 puts each feeder in its own compartment, so a failed AHU starter can be isolated while the other AHUs keep running; working beside live sections still follows site safety rules. Form 1 or 2 may force a section shutdown.
A fan wall keeps a GMP supply unit running when one fan fails, provided each fan has a backdraft damper so air cannot flow back through the stopped one. Each EC fan's rectifier adds harmonics, THDi around 35–42% with a DC choke. A single plug fan is simpler but needs a standby.
The pressure drop at which a supply AHU's final filters are changed should be the dirty-filter allowance the fan was selected for at design stage, checked at FAT and quoted in the maintenance task. Raise it later and room pressure drifts down inside its alarm band, visible only on the trend.
A cleanroom door that opens towards the lower pressure is pushed off its seal: 15 Pa on a 0.9 m by 2.1 m leaf is about 28 N. WHO's HVAC guideline says swing doors should normally open to the high-pressure side. Where escape rules differ, choose the closer for the pressure and justify the exception.
Default drive parameters will run an AHU fan but may not restart it after a power dip. Set the motor nameplate data, run the motor identification, set speed limits and ramps, add skip bands where the unit resonates, then decide and test behaviour on power loss, signal loss and fire mode. File the parameter list.