Gap-assessing a pressure cascade drawing against the installed plant

  • Engineering Solution & Consultancy
  • 1 min read

Every door on a pressure cascade drawing has a swing arrow, and on site that door should open into the higher-pressure room.

The differential then helps hold it shut. Rehang a door during a renovation to suit a new trolley route and the room pressure pushes it open against the closer instead. The drawing in the CCS usually still shows the old arrow.

That is the first of four things to check room by room when a gap assessment reaches the cascade:

  1. Door swings against the arrows, and closers that actually shut against the differential.
  2. BMS setpoints against the drawing. A room drawn at 15 Pa and controlled at 12 may still pass, but the drawing and the qualification report now describe different rooms.
  3. Alarm limits and delays in the EMS against the values the CCS justifies, with a record of who changed them and when.
  4. Transmitter references. Each differential pressure transmitter should measure the pair of rooms the drawing says it does. After a wall moves, a reference tube can end up in the wrong room and the reading stays plausible.

Walk it with the drawing in one hand and the BMS screen open, and mark every difference before deciding which side is wrong. Sometimes the plant is right and the drawing needs a change request.

A gap assessment that starts from the CCS follows each claim to the drawing, the test and the installed plant. Periodic requalification is part of our maintenance service.

Industries

Related

More on this subject

Periodic evaluation is a review, not a rerun

EU GMP Annex 11 periodic evaluation asks whether a computerized system is still valid and compliant. Most of the evidence already exists in change control, deviation and incident records and the upgrade history. Review first, then retest only the functions the review shows are affected.

InsightRead

Remote monitoring for a GMP maintenance contract

A maintenance contractor's remote view should be read-only, with setpoints changed only under the site's change control. Its alerts watch the plant behind the room, such as fan speed, filter pressure drop and chilled water temperature, and the escalation path to site is written before the contract starts.

InsightRead

Requalification and calibration on one calendar

Requalification and calibration usually run on separate schedules with separate owners. Put them on one calendar: calibrate room sensors before requalifying, check test instrument certificates at pre-test approval, and assess the impact on every result when a sensor fails calibration.

InsightRead