Scan rate and overlap in an installed HEPA leak test

  • News
  • 1 min read

Moving at 5 cm/s, a probe with a 3 cm opening spends 0.6 seconds over any point on a filter. Triple the speed and it is 0.2 seconds.

That dwell time is the whole problem with a fast scan. The photometer needs time to respond, and a leak plume has to sit inside the probe opening long enough to register. A pinhole in the middle of the media makes a strong, steady plume and is hard to miss. A frame leak is a thin line along the gasket or the edge of the frame, room air dilutes it at the perimeter, and the plume that reaches the probe is weaker. Pass along that line quickly and the reading never climbs above the threshold.

The protocol should therefore state three things, each worked out for the equipment rather than copied:

  1. The maximum scan rate, calculated from the probe dimension and the instrument's response. The figures above are an example, not a standard value.
  2. Overlapping strokes, so no strip of media or frame is left between passes.
  3. A separate, slower pass around the whole perimeter, with the probe straddling the joint between filter frame and housing or grid.

When the reading rises, the operator stops and holds the probe still to confirm, instead of judging a spike on the move.

We run installed HEPA leak tests as part of cleanroom qualification.

More notes on cleanroom testing

Related

More on this subject

Seven HVAC documents, indexed before the inspection

Cleanroom inspectors ask for the same HVAC evidence: qualification report, pressure trends and alarm log, HEPA leak tests, classification and recovery, smoke studies, as-builts and change controls. Index them per room, with document number, revision and location, so the back room answers in minutes.

InsightRead

Three APS runs across all shifts, and the HVAC has to hold still

Annex 1 initial validation of an aseptic process needs at least 3 consecutive successful simulations covering all working shifts, then periodic runs twice a year per process, line and shift. The cleanroom must hold its qualified state throughout. Agree an HVAC freeze date with QA, and list in advance which jobs are like-for-like and which need an impact assessment.

InsightRead

Both states are required; only the stage is a choice

A 50 m² Grade B room needs 10 classification locations under ISO 14644-1:2015, and EU GMP Annex 1 requires them at rest against ISO 5 and in operation against ISO 7, with the smoke study in both states. Whether each run sits in OQ or PQ is for the URS and risk assessment to justify.

InsightRead