Changing from WHO-GMP to EU-GMP midway through design reopens the URS, validation master plan, DQ and drafted IQ/OQ protocols, and for sterile products the Annex 1 CCS. The market is one of five scoping questions, with the process, grades and room list, existing assets and the division needed first.
A 50 m² Grade B room needs 10 classification locations under ISO 14644-1:2015, and EU GMP Annex 1 requires them at rest against ISO 5 and in operation against ISO 7, with the smoke study in both states. Whether each run sits in OQ or PQ is for the URS and risk assessment to justify.
EU GMP Annex 1 calls separate entry and exit change rooms for Grade B desirable. One room saves area but relies on procedure at the busiest shift change; two rooms give one-way flow at the cost of doors, air and qualification. On a new build, start from two.
GAMP 5 software categories are 1, 3, 4 and 5; firmware stopped being Category 2 in 2008. Validation effort rises with each step, and a configured Category 4 SCADA can still hold Category 5 scripts that need custom-code testing. The 2022 Second Edition kept the categories.
Requalification and calibration usually run on separate schedules with separate owners. Put them on one calendar: calibrate room sensors before requalifying, check test instrument certificates at pre-test approval, and assess the impact on every result when a sensor fails calibration.
A spreadsheet that calculates F0, an assay result or an airflow figure is a computerized system under EU GMP Annex 11 once its answer drives a GMP decision. Locked formula cells, one released template under version control and formulas checked once by hand are the minimum an auditor will look for.
Cleanroom inspectors ask for the same HVAC evidence: qualification report, pressure trends and alarm log, HEPA leak tests, classification and recovery, smoke studies, as-builts and change controls. Index them per room, with document number, revision and location, so the back room answers in minutes.
Where a SCADA, BMS or EMS records GMP-relevant data, access control, clock synchronization, alarm records and audit trails are decided by the electrical and automation engineers. Many sites keep those parameters on a separate validated EMS. Humiley's cross-functional training covers GMP, validation and project management.
Annex 1 sets zero growth as the APS target, and any contaminated unit fails it. The environmental side of the investigation starts from viable monitoring, with HVAC and EMS trends as support, so review trends before the fill, confirm logging and clock sync, and agree which HVAC events count as interruptions.
EU GMP Annex 11 clause 3.2 makes supplier competence and reliability part of computerized system validation, with the need for an audit set by risk. For SCADA, BMS and EMS, supplier records can reduce the testing the user repeats; the URS, risk assessment and configuration tests such as alarm limits and user roles stay with the user.
EU GMP Chapter 4 expects logbooks for major or critical equipment, recording use, calibration, maintenance, cleaning and repairs with dates and names. For an AHU serving graded rooms that means qualification events, sensor calibration, filter changes with differential pressure, repairs with deviation numbers and cleaning records.
A room's pressure differential sits on the room data sheet as a design value and in the monitoring SOP as alarm limits, often written months apart. Before OQ, list every door with the RDS revision it was balanced to and the current SOP alarm limits, and close each row that disagrees.