A filter passing 5% of particles with 2% of the air slipping round its frame passes almost 7%. EN 1886 measures that bypass on the AHU casing, and class F9 allows 0.5%. Frames, gaskets, clamps and rails decide the result, so put the class on the data sheet and check it at FAT.
A hygienic AHU that passes FAT clean can still reach start-up full of site dust and condensation. Factory-fitted caps, wrapping that sheds rain without trapping moisture, desiccant for shipping, dry covered storage and an internal inspection before the first fan run protect what the FAT proved.
Airflow and kW alone leave a fresh-air coil's leaving dew point to the vendor's software. A comparable coil line adds entering dry and wet bulb at the wet-season design case, leaving dry bulb and dew point, chilled water temperatures, maximum face velocity and maximum air-side pressure drop.
ISO 16890 rates filters as ePM10, ePM2.5 or ePM1, and broadly a filter must remove at least 50% of that particle fraction to earn the group. In a GMP air handling unit the pre-filter grade sets how fast the terminal HEPA loads, and so how often it is replaced and leak-tested.
Custom AHU factory slots can go before the design is final. A capacity reservation holds capacity and a delivery window against the owner's spec-freeze date: airflow and static pressure, coil duties, arrangement, EN 1886 casing classes and controls. A firm order placed too early turns each later design change into a priced variation.
Taking one AHU out of a running GMP plant changes the leakage balance of the rooms next door, and a 10 Pa step between grades can fall away. Seal shared air paths first, trim return dampers on the boundary rooms, record their original positions and keep EMS alarm limits at validated values.
Cooling coils foul on the air-entering face, while water and growth appear on the leaving side over the drain pan. A hygienic AHU needs access sections upstream and downstream of the coil and a sloped, reachable drain pan that extends past the leaving face.
A 4 × 4 kW EC fan wall draws about 27.2 A, and Humiley's sizing note puts it on one 25 A active filter module against a design target of THDi ≤ 5% at the PCC. Eight fans draw about 54.4 A and take two 25 A modules in parallel as master and slave.
A loaded filter sheds part of its dust cake when the clamps release. Withdraw it through the upstream access section or sideways through a casing door, never through the section behind it. Then check every clamp by hand and log the new filter's differential pressure as the baseline.
A plant room at 32 °C and 70% RH has a dew point near 26 °C. With 12 °C air inside, a TB3 casing frame sits at 21 to 24 °C and drips, while TB2 spans 24 to 27 °C and only its upper end clears. Ask for the tested kb and check it against the room's dew point.
At 16 fins per inch a cooling coil has a fin pitch of about 1.6 mm, and a dehumidifying coil in the tropics runs wet most of the year. Water bridges the gap, pressure drop rises, droplets carry over and film grows. At 10 fins per inch the pitch is about 2.5 mm, at the cost of a larger coil.
An old AHU leaves with loaded filters, a wet drain pan and shedding insulation. Plan the crane lift or sectional removal route, bag filters and blank ducts before it moves, hold the plant room negative while casing is cut, and watch the neighbouring suites' pressure differentials.