Closing an NCR takes more than 'rectified'

An NCR marked 'rectified' has recorded a repair. To close it properly, state the requirement that was broken, contain the item, decide the disposition and name who decided, find the cause and check for the same fault elsewhere, then verify against the original requirement and attach the evidence.

InsightRead

Commission first, qualify once

A qualification test that fails on an unsealed penetration becomes a deviation; the same finding in commissioning is a punch item. Commission and balance first, close the punch items that affect the tests, then execute IQ and OQ on systems expected to pass, turning over one AHU and its rooms at a time.