A filter changed on night shift without a leak test turns maintenance into a deviation. GMP maintenance works from criticality bands built on the asset register, planned and corrective work in one system, risk-based requalification and calibration, and 24/7 response across Southeast Asia under a maintenance agreement.
Most AHU failures appear in BMS data before they become alarms. Trend filter ΔP, fan speed or power at constant airflow, bearing vibration and temperature, and coil valve position. In a GMP plant, catching a failure as a trend turns it into planned work under change control.
Grade, temperature and humidity ranges, pressure to each neighbour, internal loads and finishes all change airflow and equipment. Agreeing a Room Data Sheet per room before layout drawings start, starting from a library of 34 standard pharma RDS, avoids redoing load calculations and AHU selections later.
EU GMP Annex 1 (2022) sets maximum requalification intervals: 6 months for Grade A and B cleanrooms and 12 months for Grade C and D. Classification, HEPA leak tests, airflow volume, pressure differentials and air velocity, or recovery where airflow is not unidirectional, are retested. A risk assessment can shorten these intervals, never extend them.
After more than twenty years with automation vendors and running an EU-GMP EPC contractor, Tony Nguyen saw problems start at the handovers between companies rather than inside any one scope. This note explains why Humiley is organized as one accountable team across design, project management, equipment and maintenance.
A hot WFI loop keeps microbes in check continuously but costs heat loss, sub-coolers at user points and faster rouging. An ambient loop with hot-water or ozone sanitization uses less energy, but the sanitization cycle must be validated and sampling must show control between cycles. Decide before the pipe is welded.
A Grade B room never retested for recovery after a ductwork change is an easy inspection finding, and six months earlier it is ordinary planned work. A written review reads Annex 1 clause by clause and gives each gap one row: clause, current state, risk, fix and rough size, finished before an inspection date is set.
Calendar maintenance gives every asset the same interval, so when hours run short the critical ones suffer with the rest. Scoring assets by the consequence of failure moves effort toward what holds a grade or a pressure cascade, and is best done once from the project's asset register.
Requalification and calibration usually run on separate schedules with separate owners. Put them on one calendar: calibrate room sensors before requalifying, check test instrument certificates at pre-test approval, and assess the impact on every result when a sensor fails calibration.
A cold room alarm that fires at every delivery soon goes unread. Plan the mapping study through a defrost cycle and a real delivery, in both seasons, then place the monitoring probe at the worst product point and set the alarm delay from how long a door-open peak actually lasts.
Monthly route-based vibration surveys catch slow fan faults such as imbalance, misalignment and bearing wear at a low cost per point. Permanent online sensors catch faults that develop between visits. Put sensors on fans whose stop takes a Grade A or B room out of spec with no standby, and route the rest.