A pass box between Grade C and Grade B is a hole in the wall with two doors on it.
Both rooms are designed around a differential of at least 10 Pa, the guidance value in EU GMP Annex 1. When a pass box door seal wears, the room pressure trend is usually where it appears first: the Grade B room dips a few pascals each time materials come through, then recovers.
The interlock does not help with that. It stops both doors opening at once, and it does nothing for a gasket that is flattened, torn or painted over. Door seals need their own line on the planned maintenance list, with an inspection interval.
A static box has no fan and no filter, so nothing inside it is diluted or replaced. Waiting does not clean it. The transfer is controlled by wiping the item and the box surfaces with disinfectant and giving that disinfectant its contact time before the clean-side door opens. Write the time into the transfer SOP.
A dynamic box has its own fan and HEPA filter. Balance its supply against both rooms so air leaves the box toward the less clean side, and put the filter on the same installed leak test schedule as the room terminals.
AeroSano pass boxes are engineered from the project's own airflow schedule and load calculation, and every unit is FAT-tested and witnessed.
Industries