An AHU design copied from Ho Chi Minh City to a site near Hanoi can miss the heating coil and the humidifier. Use ASHRAE's heating dry-bulb column to size preheat, the humidification dew point column to size the humidifier, and the dehumidification columns for the cooling coil.
Condensate leaving a fresh-air coil equals dry-air mass flow times the drop in humidity ratio. At 10,000 m³/h dried from 21 to 7 g/kg that is about 170 litres an hour. Timed at the trap on a humid day, a shortfall points at water temperature, flow or bypass.
Humidity control usually fails on a mild, saturated night at low occupancy: little sensible load, full latent load from the fresh air. A coil controlled on temperature throttles back and RH climbs. Run the case, control the coil on leaving dew point and size reheat for it.
Plot outdoor, mixed, coil-leaving, after-fan, after-reheat and room states on one psychrometric chart. A reviewer can see a mixed-air point off its line, a coil dew point without margin for the room latent load, over-drying paid for twice, and reheat oversized because fan heat was ignored.
ICH Q10 expects changes to be evaluated after implementation. Closing a change the day the part is installed skips that step. Define the effectiveness check when the change is approved: the data that shows the objective was met, a period long enough to include the original conditions, and the result that closes it.
At 40 °C condensing, the Carnot COP rises from 7.95 at 5 °C evaporating to 8.21 at 6 °C, about 3.3% per kelvin. Real chillers differ but follow the direction, so a GMP plant should not run every coil at the temperature only the fresh-air dehumidification coil needs.
A low leaving dew point can come from a deeper coil with warmer water or a compact coil with colder water. The first costs fan pressure every running hour; the second costs chiller COP, about 3% per kelvin in an ideal cycle. The cheaper option depends on hours, tariff and how much of the plant shares the water.
When a DX compressor cycles off and the fan keeps running, the water film left on the coil re-evaporates into the supply air, so net dehumidification falls short of the rating at part load. Cleanrooms cannot cycle their fans, so they need modulating or staged capacity, or chilled water.
Heating 18 °C, 60% RH air to 22 °C drops the reading to about 47% RH while the air keeps 7.7 g of water per kilogram. A room that meets RH only on reheat has no margin for one fault. Trend reheat output beside room RH: rising reheat means the coil is losing latent capacity.
Cartons and labels from an 80% RH warehouse release moisture in a 20% RH packing room. If board gives up 2% of its weight, a 500 kg delivery adds 10 kg of water. Stage packaging in a controlled area, unwrapped, for a time set by weighing sample cartons.
Air leaving a coil at 12 °C and 95% RH reads about 50% RH at 22 °C with the same 8.3 g/kg of water. A duct RH sensor after the coil works at the top of its scale. Control the coil on dew point or leaving-air temperature, and keep duct RH after reheat as a wet-filter alarm.
Reheat after a dehumidifying coil costs about 0.34 kW per 1,000 m³/h per kelvin, or 34 kW for 5 K on a 20,000 m³/h unit. Per kWh delivered, resistance and boilers cost most, heat pumps less, condenser recovery and wrap-around heat pipes least; tariffs and the site decide what fits.