The PIC/S GMP Guide and EU GMP are almost identical, revised Annex 1 included. In the EU the GMP principles are set in law and certificates sit in EudraGMDP; PIC/S authorities adopt the guide nationally and PIC/S certifies nothing. One design serves both; the EU inspection route is planned separately.
A 15–25 °C store in Viet Nam needs active cooling. Split units give cheap N+1 redundancy but a short air throw and little humidity control. A chilled-water AHU ducts air to the top of tall racking and can control dew point, with dearer redundancy. Humidity limits on the labels usually decide it.
Annex 1 expects the Contamination Control Strategy to be actively reviewed and updated. A yearly meeting catches changes late. Adding one question to every HVAC change control, EM adverse trend review and deviation closure form, asking whether the CCS still says the right thing, keeps it current with the site.
The CTD has five modules, and Module 3 (Quality) records the process, its controls and often the facility, including room grades, water grades and the conditions behind hold times. After approval, changing them generally needs a variation. Draft Module 3 and the design basis from one table and send every change to both teams.
The scope of EU GMP Annex 1 (2022) says some of its principles, including the contamination control strategy, may be used for certain non-sterile products such as liquids, creams and ointments. A semi-solids plant that writes a CCS tying room grades, flows, water and monitoring to product risk has an answer for the inspector.
When the HVAC load calculation assumes four operators and the aseptic process simulation qualifies six, the room runs outside its design basis. Write one maximum occupancy per room in the URS and carry it into the load calculation, room data sheet, APS protocol and entry SOP.
Before a product is transferred, compare what it needs with what the receiving facility has shown it can do: room grades and pressure cascade, containment, temperature and humidity from worst-month trend data, utility quality and capacity, and equipment principle and scale. WHO's guideline puts gap analysis among the first steps.
Good engineering practice is the design review, installation checks and commissioning that sit under qualification. WHO's HVAC guideline defines it, and EU GMP Annex 15 (2015) allows data from outside the manufacturer's own programs if justified and controlled. Commissioning sheets made with calibrated instruments and signed by the person who measured can then be relied on.
EU GMP Chapter 9, as it stands today, is one principle and three clauses. Listed areas should be examined to a pre-arranged program, by designated competent persons from the company working independently; every self inspection should be recorded, and so should the actions taken afterwards. The list of areas includes self inspection itself.
A URS line such as 'the HVAC system shall maintain suitable conditions' cannot be tested. EU GMP Annex 15 (2015) says the URS should be a point of reference throughout the validation life cycle. Five checks make a line usable: one requirement, a unique ID, a number with unit and tolerance, the state, and a named test.
A humidifier fed from the plant boiler injects the boiler's volatile treatment chemicals into the supply air. WHO's HVAC guideline for non-sterile products says chemicals that could have a detrimental effect on the product should not be added to the boiler system. Use a clean steam generator or a steam-to-steam humidifier, or assess every chemical, and state the steam quality in the URS.
The 2013 text of EU GMP Chapter 1 lists the qualification status of relevant equipment and utilities among the items a product quality review should include. Engineering can make that line believable with four more inputs: changes in the period, excursions and trends, calibration and maintenance failures with product impact, and the status of engineering CAPAs.