Heating 18 °C, 60% RH air to 22 °C drops the reading to about 47% RH while the air keeps 7.7 g of water per kilogram. A room that meets RH only on reheat has no margin for one fault. Trend reheat output beside room RH: rising reheat means the coil is losing latent capacity.
A 100 cm² door gap at 15 Pa passes about 110 m³/h, but only doors on the suite boundary cost fresh air. Internal door leakage returns through the neighbouring room's grille. For twenty doors with four on the boundary, the leakage to make up is 440 m³/h rather than 2,200 m³/h of wet tropical air.
Cooling tower leaving water equals wet-bulb plus approach, and each kelvin of condenser water costs compressor power. At a 2–3% per kelvin rule of thumb, one extra kelvin of approach on a chiller drawing 180 kW is about 4.5 kW, or roughly 36,000 kWh over 8,000 running hours.
Reheat after a dehumidifying coil costs about 0.34 kW per 1,000 m³/h per kelvin, or 34 kW for 5 K on a 20,000 m³/h unit. Per kWh delivered, resistance and boilers cost most, heat pumps less, condenser recovery and wrap-around heat pipes least; tariffs and the site decide what fits.
Light office wear is about 0.5 clo, while full cleanroom gowning sits nearer 1.0 clo, and standing line work is about 1.6 met or more. Gowned operators are comfortable cooler than office staff, so set the room temperature in the URS with QA and EHS before the load calculation sizes the coil.
A full-size 592 × 592 mm bag filter is commonly rated at about 3,400 m³/h. A 20,000 m³/h AHU needs six frames; a casing with room for four runs each at 47% over, with higher pressure drop, possibly lower efficiency and fluttering pockets. The frame count belongs in the specification and the FAT.
When cooling and reheat valves open together at 20 ± 0.5 °C, the cause is usually a zero gap between the two control sequences. Check the trend first. Where the product data supports 20 ± 2 °C, cooling above 21 °C and reheat below 19 °C let the room drift between with both valves shut.
Ten per cent on the load, on the airflow and on the coil multiplies to 1.33, because each margin sits on the one before. The oversized coil runs at part load most of the year, condenses less water, and RH climbs while temperature holds. One named margin and a part-load check avoid it.
A test at minimum fan speed with a door held open is OQ evidence; PQ shows normal operation, with production or a representative simulation, over a stated period. A step that forces a condition usually belongs in OQ, and separate protocols allow OQ to close before PQ starts.
At a 6 K difference each kW of cooling needs about 0.14 m³/h of chilled water, so 500 kW moves about 72 m³/h. When return water falls to 10 °C the same load needs 50% more water and, on a fixed system, about 3.4 times the pump power. Two-way valves and a watched return temperature protect the design difference.
IQ verifies an installation against the approved drawings. When site changes are not red-lined and reviewed, IQ either raises late deviations or signs off drawings that no longer match the plant. Reviewed as-builts belong in the turnover package before IQ starts.
Measuring every room against one reference stops errors stacking but leaves room-pair differences at up to ±2 Pa with ±1 Pa sensors. Room-to-room sensors show airflow direction directly but add errors along the chain. Record one set, compute the other, and state the error budget.