A desiccant wheel sized for wet-season fresh air can over-dry a tight-band room in the dry season. At 21 °C and 30% RH, ±2% RH is a dew point window about 2 K wide. Specify reactivation-heat turndown to the dry-season load, a second control lever, and check the band in both seasons.
A catalogue AHU suits an office zone or a like-for-like swap. Where humidity is specified it needs checking: a room at 20 °C and 45% RH has a dew point of about 7.7 °C, and a range coil can meet total kW yet leave the air wetter. Ask for leaving-air dew point at the site's peak condition.
A cooling coil dries air only to about its fin temperature; below 0 °C the fins frost. Dry rooms rely on desiccant rotors, down to −60 °C dew point, with a precooling coil removing bulk moisture cheaply first. Where that split sits sets most of the dry room's energy bill.
Score the technical envelope of a cleanroom HVAC tender and sign it off before any price is opened. Issue the scoring sheet with the tender: mandatory items pass or fail, the rest weighted, for example 40% technical depth and 20% each for documentation, delivery and service. Score every listed deviation.
Airflow and kW alone leave a fresh-air coil's leaving dew point to the vendor's software. A comparable coil line adds entering dry and wet bulb at the wet-season design case, leaving dry bulb and dew point, chilled water temperatures, maximum face velocity and maximum air-side pressure drop.
A desiccant rotor is the right tool for deep drying and an expensive one for bulk moisture. In tropical fresh air, a pre-cooling coil ahead of the rotor removes most of the water by condensation, so the rotor can be smaller, use less regeneration heat and hold its leaving condition more steadily.
A plant room at 32 °C and 70% RH has a dew point near 26 °C. With 12 °C air inside, a TB3 casing frame sits at 21 to 24 °C and drips, while TB2 spans 24 to 27 °C and only its upper end clears. Ask for the tested kb and check it against the room's dew point.
In a tropical plant the wet zone of a fresh-air AHU runs from the cooling coil and drain pan to the reheat coil. Specify stainless there, 316 where chlorine agents are used. Fan, pre-filter and mixing sections can be coated galvanised if cut edges are sealed. Ask for weld and passivation records.
At −60 °C dew point air holds about 0.007 g of water per kilogram, roughly 3,000 times less than outdoor air in southern Viet Nam. By a rough sum, 1 m³/h of leakage uses up around 4,000 m³/h of dry supply air, so the envelope, airlocks and occupancy belong in the dryer specification.
A 50 mm PU-core AHU panel can match a 60 mm mineral wool panel on heat loss, but PU is combustible and mineral wool is not. In a humid plant room, condensation starts at the frame's thermal bridges whatever the core. Decide fire class first, then the EN 1886 TB class, then thickness.
EN 1886 classes AHU casing strength by deflection at test pressure: D1 up to 4 mm/m, D2 up to 10 mm/m. On a high-static GMP supply unit, a flexing panel works its gaskets loose and leakage rises. Ask which class was tested, on what model box, and whether your design pressure fits.