A catalogue AHU suits an office zone or a like-for-like swap. Where humidity is specified it needs checking: a room at 20 °C and 45% RH has a dew point of about 7.7 °C, and a range coil can meet total kW yet leave the air wetter. Ask for leaving-air dew point at the site's peak condition.
Near the sea or heavy industry, condensate turns a copper-tube, aluminium-fin coil into a galvanic cell and the fin bond fails first. Coatings applied after assembly cover the cut edges that pre-coated fin stock leaves bare and the collars where its coating cracks. Select the coil with the maker's correction factor and ask for the salt-spray report.
A FAT witness needs the approved drawings and datasheets at the order revision, the approved protocol with numeric criteria, the specification clause list, the expected test instrument list and an agreed punch-list format with someone authorised to sign it. Without these, a witness can only watch.
Low-level returns sweep particles down and out past the work, but each grille needs a riser to the ceiling void. Some modular wall systems can carry it inside the panel, flush with the room; ask before the layout is drawn. Use tool-free grilles, spread returns along the walls and seal the joints.
Masonry with epoxy paint is cheaper to build, but every later penetration in a classified room means drilling, repainting, cleaning and a particle count under change control. Before choosing, count how often each type of room in your current plant changed in the last five years; rooms that changed more than once usually repay panels.
Neither an EN 10204 3.1 nor a 3.2 helps if the heat number is cut off a pipe before it is transferred. A 3.1 is validated by the manufacturer's independent inspector; a 3.2 adds a purchaser's or regulatory inspector at extra cost and lead time. Ask for 3.2 where the URS or a part's design code requires it.
IEC 61439-2 defines four forms of internal separation in a switchboard. Form 4 puts each feeder in its own compartment, so a failed AHU starter can be isolated while the other AHUs keep running; working beside live sections still follows site safety rules. Form 1 or 2 may force a section shutdown.
On an equipment-only AHU purchase, write the EN 1886 casing leakage class and F9 filter bypass into the order, witness the leakage test on the built unit at FAT, check the selection against the project airflow schedule, and require the equipment file compiled during production so IQ starts complete.
Steam that has not absorbed before it meets a filter, fan or sensor leaves them wet. Take the absorption distance from the maker at the unit's real air speed and load, keep wet-sensitive parts beyond it, fit a trapped stainless drain pan and access, and add a downstream high-limit sensor.
AHU casing classes such as L1 leakage or TB2 thermal bridging usually come from a standard EN 1886 model box. The unit on site has more doors, joints and penetrations. At FAT, check them on the real unit, especially filter frame gaskets: bypass around the fine-filter frames loads the terminal HEPA filters faster.
A ±5% airflow tolerance cannot be tested until the specification says where it is measured, with which instrument and at which filter condition. Fan inlet, duct traverse and terminal hood readings can differ by more than the tolerance. Write the method in the same sentence as the number.