Run-to-failure in a GMP plant: rule out hidden failures first

  • Maintenance Service
  • 1 min read

A seized standby pump looks exactly like a healthy one until the duty pump trips. No run-to-failure list should ever carry it.

Run-to-failure is a legitimate maintenance strategy: the asset gets no planned work, and when it fails it is replaced. It only works when the failure announces itself. A hand dryer in a changing room outside the GMP area stops, someone reports it that day, and a new one goes up. A standby pump, a fire damper or a smoke detector fails silently, and the first sign is the day it was needed. Those assets need a test on a set interval.

With hidden failures ruled out, an asset can go on the list when:

  1. Its failure is evident at once to the people who use it.
  2. It has no effect on product, a room grade, a pressure cascade or GMP data.
  3. Replacing it costs less than the planned work it would otherwise get.
  4. A spare or a supplier can restore it within a time the users agree to.

Write the decision into the criticality assessment, one line per asset with the reason, signed by engineering, so an auditor can see which assets were left alone on purpose. Review a line when the asset's duty changes: a wall fan moved from the admin corridor into the UPS room has left the list.

Our maintenance plans are built from the project's asset register and criticality assessment, and that is where these lines go.

Industries

Related

More on this subject

Periodic and event-driven requalification

A new AHU on a running suite moves the pressure cascade, so its event-driven requalification reaches the differential at every door it serves. Change control sets that scope. Annex 1 (2022) separately caps periodic cleanroom intervals at 6 months for Grade A and B and 12 for C and D.

InsightRead

EU GMP Annex 1 (2022) sets maximum requalification intervals: 6 months for Grade A and B cleanrooms and 12 months for Grade C and D. Classification, HEPA leak tests, airflow volume, pressure differentials and air velocity, or recovery where airflow is not unidirectional, are retested. A risk assessment can shorten these intervals, never extend them.

InsightRead