Before detail design opens, a GMP project should have frozen room data sheets and pressure cascade, loads that match the equipment list, a URS for each critical system and owned open items. A cascade change after the ducts are drawn reaches the duct sizes, terminal filters, AHU selection and every neighbouring pressure step.
Taking one AHU out of a running GMP plant changes the leakage balance of the rooms next door, and a 10 Pa step between grades can fall away. Seal shared air paths first, trim return dampers on the boundary rooms, record their original positions and keep EMS alarm limits at validated values.
Monthly route-based vibration surveys catch slow fan faults such as imbalance, misalignment and bearing wear at a low cost per point. Permanent online sensors catch faults that develop between visits. Put sensors on fans whose stop takes a Grade A or B room out of spec with no standby, and route the rest.
EU GMP Chapter 4 expects logbooks for major or critical equipment, recording use, calibration, maintenance, cleaning and repairs with dates and names. For an AHU serving graded rooms that means qualification events, sensor calibration, filter changes with differential pressure, repairs with deviation numbers and cleaning records.
Plants in northern Viet Nam can need winter humidification. In a GMP AHU a steam humidifier adds vapour with no liquid water, at roughly 0.72 kWh per kg from 20 °C water, provided it is fed clean steam, since plant boiler steam can carry amines. Adiabatic units carry a water-treatment and microbial burden and need more reheat.
In a GMP plant a work order is the record that equipment went back into service in its qualified state. Before it closes it needs as-found and as-left values, parts by number, technician sign-off with accountable review, and links to any deviation or change control, all kept under an Annex 11 audit trail.
Operating theatres and isolation rooms rarely get a shutdown window, so maintenance fits between surgery lists. An isolation room may hold only 2.5 Pa negative, which one open ceiling panel next door can erase. Plan the dampers that hold the neighbours, the dirty-filter route and the tests before handback.
Shrinking a 10,000 m³/h duct from 700 × 500 mm to 600 × 400 mm raises velocity from about 8 to 12 m/s and velocity pressure from 38 to 80 Pa, so every fitting costs about twice. Set separate limits for mains and branches in the design basis.
An old AHU leaves with loaded filters, a wet drain pan and shedding insulation. Plan the crane lift or sectional removal route, bag filters and blank ducts before it moves, hold the plant room negative while casing is cut, and watch the neighbouring suites' pressure differentials.
For a 10,000 m³/h AHU in Ho Chi Minh City, full fresh air needs about 180 kW at the coil and 20% fresh air about 60 kW. WHO's HVAC guideline for non-sterile products allows recirculation where filtration and a risk assessment support it, with a written case per system.
EU GMP Annex 15 section 3 asks for design compliance with GMP to be demonstrated and documented, with URS requirements verified during DQ. Meeting minutes rarely do that. A DQ report traces every URS line to a drawing, calculation or datasheet at a stated revision, with a verdict and a signature.
In a GMP air handling unit, a wheel carries some exhaust into the supply by design, and a purge sector only reduces it. Run-around coils keep the streams apart at lower recovery. Plate exchangers leak in the direction the fan positions set, so mark and measure the pressure on each side before and at commissioning.