In the wet season, outdoor air at 29 °C and a 26 °C dew point carries about 84 kJ/kg, against about 37 kJ/kg for cleanroom return air at 20 °C / 45% RH. Economiser hours are close to zero; tropical savings come from dehumidification strategy, avoided reheat, fan power and chiller lift.
A 20 °C / 45% RH room has a dew point near 7.7 °C. A recirculation coil on 12 °C water stays dry; on 6 °C water it condenses, dehumidifies against the fresh-air unit and needs a wet drain pan. The dry coil is larger and needs a second water temperature.
Mapping protocols from temperate countries ask for summer and winter studies. In southern Viet Nam the real extremes are the hot dry months, which test temperature, and the rainy season, which tests humidity and latent cooling load. Two mappings timed to the local calendar give an inspector a record worth reading.
A chilled-water valve with 10 kPa across it on a 40 kPa coil branch has an authority of 0.2. At part load it sits near its seat, hunts, and the cleanroom dew point swings. Size the valve drop close to the branch drop, aim near 0.5, and check the opening at minimum load.
A cooling coil dries air only to about its fin temperature; below 0 °C the fins frost. Dry rooms rely on desiccant rotors, down to −60 °C dew point, with a precooling coil removing bulk moisture cheaply first. Where that split sits sets most of the dry room's energy bill.
Bringing 10,000 m³/h of outdoor air from 29 °C / 26 °C dew point to 10 °C / 9 °C dew point takes about 186 kW of cooling, two-thirds of it condensing roughly 170 kg of water an hour. Fresh-air and exhaust quantities deserve the same scrutiny as filter grades.
NMP's lower explosive limit is about 1.3% by volume. Held below 25% of it, an oven evaporating 100 kg/h of NMP needs around 7,500 m³/h of exhaust. The make-up air, its dew point and the coating hall to dry room pressure step should be sized from the same evaporation figure.
Score the technical envelope of a cleanroom HVAC tender and sign it off before any price is opened. Issue the scoring sheet with the tender: mandatory items pass or fail, the rest weighted, for example 40% technical depth and 20% each for documentation, delivery and service. Score every listed deviation.
At −60 °C dew point a coil would freeze, so a desiccant rotor does the drying and regeneration air, often heated to around 120–140 °C, is the running cost. Pre-cooling ahead of the rotor, heat recovery, staging with the real crew size and a tight envelope are all set at design stage.
Before the supply fan is selected, check whether the coil sheet quotes a wet or a dry air pressure drop, and read it with the entering condition: dry- and wet-bulb at the peak dew point case. Then check leaving dew point against room RH, face velocity below about 2.5 m/s and a realistic chilled-water ΔT.
At 22 °C and 45% RH, a 1 K temperature rise moves RH by about 2.5 points with no change in moisture. Hygroscopic products need staged drying controlled on dew point or RH, with the control sensor in the room, not a warm return duct. Humiley desiccant dehumidification is built to ±2% RH control.
Airflow and kW alone leave a fresh-air coil's leaving dew point to the vendor's software. A comparable coil line adds entering dry and wet bulb at the wet-season design case, leaving dry bulb and dew point, chilled water temperatures, maximum face velocity and maximum air-side pressure drop.