"Type-tested" is IEC 60439 wording. IEC 61439-1 separates design verification (Clause 10), which proves the assembly system once, from routine verification (Clause 11), which checks every panel built. At FAT a buyer should receive the design verification report and a routine record tied to the panel serial number.
AHU casing classes such as L1 leakage or TB2 thermal bridging usually come from a standard EN 1886 model box. The unit on site has more doors, joints and penetrations. At FAT, check them on the real unit, especially filter frame gaskets: bypass around the fine-filter frames loads the terminal HEPA filters faster.
Airlock door interlocks protect a 10–15 Pa step between grades; a fire needs the doors to open. Specify both together: interlock logic, status lamps, fire-alarm release, fail-safe locks, a logged BMS alarm on every override, and a release tested at FAT, at OQ and periodically.
A ±5% airflow tolerance cannot be tested until the specification says where it is measured, with which instrument and at which filter condition. Fan inlet, duct traverse and terminal hood readings can differ by more than the tolerance. Write the method in the same sentence as the number.
A 50 mm PU-core AHU panel can match a 60 mm mineral wool panel on heat loss, but PU is combustible and mineral wool is not. In a humid plant room, condensation starts at the frame's thermal bridges whatever the core. Decide fire class first, then the EN 1886 TB class, then thickness.
Filter transmitters get bought twice, or not at all, when the tender never says who supplies them. An AHU/BMS interface schedule lists every sensor, drive signal, actuator and fire alarm contact with who supplies, mounts, wires and configures it, attached to both tenders before they go out.
The installed HEPA scan covers media, frame and the filter-to-housing seal, but not the flange between housing and ceiling. Where the ceiling void runs at higher pressure than the room, unfiltered air enters there. Seal it with an evenly compressed gasket and sealant bead, then probe the flange and file the result.
The pressure drop at which a supply AHU's final filters are changed should be the dirty-filter allowance the fan was selected for at design stage, checked at FAT and quoted in the maintenance task. Raise it later and room pressure drifts down inside its alarm band, visible only on the trend.
When a terminal label disagrees with the drawing, fault-finding turns into guessing. At FAT, trace ten random wires end to end, read device tags against the drawing and bill of materials, and confirm the door-pocket drawing carries the same revision as the equipment file. After site changes, return marked-up drawings.
An FFU array can average 0.45 m/s and still have a corner at 0.30 m/s. Measure each unit on a grid at FAT with fan speed settings recorded, then repeat the grid across the installed array at OQ. A flat map is healthy; a low edge points at speed, plenum, blanking or lights.
EN 1886 classes AHU casing strength by deflection at test pressure: D1 up to 4 mm/m, D2 up to 10 mm/m. On a high-static GMP supply unit, a flexing panel works its gaskets loose and leakage rises. Ask which class was tested, on what model box, and whether your design pressure fits.
A spring isolator with its transport bolt still fitted transmits everything. Remove transport locks, select isolators for the lowest drive speed, keep flexible connections slack, remove rigid bridges such as conduit or drain lines, use inertia bases where needed, and file the balance report and a vibration baseline.