The HEPA housing joint the filter scan misses

The installed HEPA scan covers media, frame and the filter-to-housing seal, but not the flange between housing and ceiling. Where the ceiling void runs at higher pressure than the room, unfiltered air enters there. Seal it with an evenly compressed gasket and sealant bead, then probe the flange and file the result.

InsightRead

Manufacturing & Distribution

Panel labels that match the drawing

When a terminal label disagrees with the drawing, fault-finding turns into guessing. At FAT, trace ten random wires end to end, read device tags against the drawing and bill of materials, and confirm the door-pocket drawing carries the same revision as the equipment file. After site changes, return marked-up drawings.

InsightRead

An FFU array can average 0.45 m/s and still have a corner at 0.30 m/s. Measure each unit on a grid at FAT with fan speed settings recorded, then repeat the grid across the installed array at OQ. A flat map is healthy; a low edge points at speed, plenum, blanking or lights.

InsightRead

Manufacturing & Distribution

AHU casing deflection: D1 or D2

EN 1886 classes AHU casing strength by deflection at test pressure: D1 up to 4 mm/m, D2 up to 10 mm/m. On a high-static GMP supply unit, a flexing panel works its gaskets loose and leakage rises. Ask which class was tested, on what model box, and whether your design pressure fits.

InsightRead

Manufacturing & Distribution

AHU vibration isolation, link by link

A spring isolator with its transport bolt still fitted transmits everything. Remove transport locks, select isolators for the lowest drive speed, keep flexible connections slack, remove rigid bridges such as conduit or drain lines, use inertia bases where needed, and file the balance report and a vibration baseline.