An AHU design copied from Ho Chi Minh City to a site near Hanoi can miss the heating coil and the humidifier. Use ASHRAE's heating dry-bulb column to size preheat, the humidification dew point column to size the humidifier, and the dehumidification columns for the cooling coil.
Steam that has not absorbed before it meets a filter, fan or sensor leaves them wet. Take the absorption distance from the maker at the unit's real air speed and load, keep wet-sensitive parts beyond it, fit a trapped stainless drain pan and access, and add a downstream high-limit sensor.
Condensate leaving a fresh-air coil equals dry-air mass flow times the drop in humidity ratio. At 10,000 m³/h dried from 21 to 7 g/kg that is about 170 litres an hour. Timed at the trap on a humid day, a shortfall points at water temperature, flow or bypass.
Humidity control usually fails on a mild, saturated night at low occupancy: little sensible load, full latent load from the fresh air. A coil controlled on temperature throttles back and RH climbs. Run the case, control the coil on leaving dew point and size reheat for it.
A room held at 45% RH ±2% is really at 47% when its sensor has drifted 2% low, and the BMS still shows 45%. Tight bands need sensor accuracy and reference accuracy tighter than the band, calibration near the setpoint, evidence-based intervals and as-found records.
Plot outdoor, mixed, coil-leaving, after-fan, after-reheat and room states on one psychrometric chart. A reviewer can see a mixed-air point off its line, a coil dew point without margin for the room latent load, over-drying paid for twice, and reheat oversized because fan heat was ignored.
ICH Q10 expects changes to be evaluated after implementation. Closing a change the day the part is installed skips that step. Define the effectiveness check when the change is approved: the data that shows the objective was met, a period long enough to include the original conditions, and the result that closes it.
After an AHU failure, QA decides on product from one report. It needs a timeline built from BMS and EMS timestamps, trend exports for every affected room, the impact on rooms and batches, and a CAPA with owners and dates. All four can be drafted before the day shift starts.
A tablet press's dust extraction pulls air out of the compression room; leave it off the room data sheet and the corridor pressure shifts whenever it runs. Granulation adds moisture and sometimes solvent, coating adds heat and its own air system. List every load before sizing supply air.
A 50 mm PU-core AHU panel can match a 60 mm mineral wool panel on heat loss, but PU is combustible and mineral wool is not. In a humid plant room, condensation starts at the frame's thermal bridges whatever the core. Decide fire class first, then the EN 1886 TB class, then thickness.
Desiccant rotors lose capacity slowly: worn sector seals let wet air cross over, a slipping drive slows the rotor, dust and solvent vapour foul the media. Measuring outlet dew point, airflow and reactivation temperature against the commissioning record shows the trend before a −60 °C dry room does.
At 40 °C condensing, the Carnot COP rises from 7.95 at 5 °C evaporating to 8.21 at 6 °C, about 3.3% per kelvin. Real chillers differ but follow the direction, so a GMP plant should not run every coil at the temperature only the fresh-air dehumidification coil needs.