300 TR is about 1,055 kW, some 55 kW more than a 1,000 kW offer, enough to use up a 5% design margin. Converting fixes the unit only. Capacity also depends on leaving chilled-water and condenser conditions, so ask every vendor for figures at your design conditions, in one table.
New slabs, screeds and plaster release water into the room for weeks after the HVAC starts. Tuning controls or running OQ humidity tests through that load measures the building drying out. Plan a dry-out period, trend RH and dew point daily, and start humidity OQ once the trend flattens.
Above about 2.5 m/s face velocity, a wet cooling coil carries water onto the next section, a microbial risk in a hygienic AHU. A smaller coil face saves casing size but adds an eliminator, higher pressure drop and fan energy. At 5 m³/s, 2.5 m/s needs a 2 m² face.
Recirculated cleanroom air returns near room condition and needs almost no dehumidification. In a worked wet-season example, 10,000 m³/h of fresh air costs about 186 kW of coil load. Remove avoidable fresh air from exhaust, leakage and over-pressurisation before investing in heat recovery devices.
When the fresh-air unit does all the drying and room AHU coils stay dry, every room's humidity depends on that one unit. Size its coil on the wet-season coincident condition, control on off-coil dew point, and decide in the design basis what happens when it trips.
In the wet season, outdoor air at 29 °C and a 26 °C dew point carries about 84 kJ/kg, against about 37 kJ/kg for cleanroom return air at 20 °C / 45% RH. Economiser hours are close to zero; tropical savings come from dehumidification strategy, avoided reheat, fan power and chiller lift.
A 20 °C / 45% RH room has a dew point near 7.7 °C. A recirculation coil on 12 °C water stays dry; on 6 °C water it condenses, dehumidifies against the fresh-air unit and needs a wet drain pan. The dry coil is larger and needs a second water temperature.
Mapping protocols from temperate countries ask for summer and winter studies. In southern Viet Nam the real extremes are the hot dry months, which test temperature, and the rainy season, which tests humidity and latent cooling load. Two mappings timed to the local calendar give an inspector a record worth reading.
Cleanroom load calculations fail on their inputs: nameplate equipment heat, table lighting density, office-level occupancy, missing process heat and forgotten fan heat, about 2 K at 1,500 Pa. Vendor heat-release data, the lighting design and the process description give better numbers than any default.
A desiccant dehumidifier selection depends on six inputs: fresh and return airflow, air condition after pre-cooling, target dew point, reactivation heat source, leakage allowance and redundancy. −40 °C dew point is about 0.08 g/kg and −60 °C under 0.01 g/kg, a step that can add a rotor stage.
Where a SCADA, BMS or EMS records GMP-relevant data, access control, clock synchronization, alarm records and audit trails are decided by the electrical and automation engineers. Many sites keep those parameters on a separate validated EMS. Humiley's cross-functional training covers GMP, validation and project management.