Filter loading can swing AHU resistance from 250 Pa clean to 450 Pa at change-out while airflow must stay constant. Selecting near 350 Pa and checking design airflow at 450 Pa with the drive at full speed avoids both a fan stuck right of peak and an airflow shortfall. The energy difference is modest.
A 10 m stairwell at a 10 K temperature difference produces about 4 Pa of stack effect, and a door near the top or bottom can see up to half of it, a noticeable part of a 10–15 Pa cascade step. Shafts that open onto clean corridors make the cascade drift with floor, weather and door position.
Duct airtightness classes A to D each allow about a third of the leakage of the class before. At 400 Pa, 500 m² of class B ductwork may leak about 220 l/s, class C about 75 l/s. Leakage after the flow control point moves the pressure cascade without the controller noticing.
A cleanroom is qualified on its supply airflow: air change rate, recovery time and hood velocity. Controlling room pressure by trimming supply moves those numbers with every door opening. Holding supply constant and modulating extract or return keeps the qualified airflow and still holds the pressure cascade.
For the same excess airflow, room pressure differential varies with the inverse square of the leakage area. On a finished cleanroom that area hides in door gaps, ungasketed light fittings, open socket boxes, panel joints and penetrations. Compare measured excess air with the design allowance at commissioning.
During start and stop, whichever fan moves first decides which way air flows through the door gaps. Positive suites start supply first and stop extract first; containment suites do the opposite. Interlock the order, define the response to a single fan trip and test it at OQ with a real power cut.
A URS line such as at least 10 Pa above a Grade C corridor sets the airflow offset, the door leakage allowance, the pressure control range, the alarm limit and the OQ acceptance criterion, when the URS and validation strategy are written in parallel with the design.
Under NAMUR NE 43, a 4–20 mA loop is valid between 3.8 and 20.5 mA; 3.6 mA or below, or 21 mA or above, signals a fault. Configure the EMS to show those as bad quality and alarm, never the last good value, and detect stale values on digital links too.
Humidity control usually fails on a mild, saturated night at low occupancy: little sensible load, full latent load from the fresh air. A coil controlled on temperature throttles back and RH climbs. Run the case, control the coil on leaving dew point and size reheat for it.
When one location in a Grade C room recovers far slower than the rest, raising a 60 m³ room from 20 to 30 air changes adds 50% more air and may barely help. A smoke study usually shows short-circuiting to a return; moving or adding a low-level return is the cheaper fix.
When a DX compressor cycles off and the fan keeps running, the water film left on the coil re-evaporates into the supply air, so net dehumidification falls short of the rating at part load. Cleanrooms cannot cycle their fans, so they need modulating or staged capacity, or chilled water.