On multi-contractor sites the decisions between scopes go unowned first: envelope penetrations, punch-list closure, construction cleanliness, interface as-builts and turnover sign-off. A RACI works when it names those decisions, with one accountable person each, and is reviewed whenever a scope changes.
In an FMEA risk register, severity 10, occurrence 2 and detection 3 score an RPN of 60, below a nuisance risk at 100. Add a rule that any severity 9 or 10 comes to the weekly review whatever its RPN, and re-rate every risk after its mitigation.
A weekly FMEA review earns its time only when it ends in decisions. Ask the same five questions every week: what is new, which scores moved and why, who owns each open risk, what the next action is and when, and what can be closed on evidence.
Two accountable parties on one RACI row means nobody decides. The rows most likely to collect two As cross a handover: design changes after tender, vendor drawing approval, long-lead releases and readiness for IQ. Read every row as "X decides" and fix the ones that need two names before kickoff.
Two independent long-lead paths, each 80% likely on time, give a 64% chance that both arrive for qualification. A qualitative FMEA register manages risks one at a time; a Monte Carlo schedule analysis adds them up and gives P50 and P80 dates. It earns its cost where paths converge on a fixed date.
Most of a cleanroom HVAC contract is paid before the turnover documents exist. Split the retention into two parts, released on acceptance of the turnover package and of the documents, and size the documentation part on what it would cost the owner to finish as-builts, calibrations and retests without the contractor.
Forty change orders at 0.5% each add up to a 20% overrun nobody approved. An owner's change log needs a pricing deadline written into the contract, signed approval of cost and time before work starts, and a running total on budget and completion date that the owner reads every week.
EPC moves cost and schedule risk to one contractor at a fixed price; compliance risk stays with the owner under any contract form. If the tender never named who writes and executes the DQ, IQ, OQ and PQ protocols, the lump sum did not include them. Owners who cannot define that yet are often better served by EPCM.
An owner's monthly report needs four pages: schedule, cost, earned value and risk, each answering its question on the top line. Show forecast at completion, SPI and CPI trends with a review trigger agreed in advance, and the top FMEA risks with owners. Slipped long-lead items go on page one.
Contingency reserve covers risks already on the register, sits inside the cost baseline and is drawn by the project manager against a named risk. Management reserve covers what nobody has listed, sits outside the baseline and is released by the owner through a change. Mixing them empties the pot before the risk arrives.
Percent complete is an opinion; earned value is a measurement. Stage gates from concept to PQ, monthly SPI and CPI reporting, a live FMEA risk register reviewed weekly and a RACI the owner's QA team has seen give a pharma project governance that is used, not filed.