A cleanroom is qualified on its supply airflow: air change rate, recovery time and hood velocity. Controlling room pressure by trimming supply moves those numbers with every door opening. Holding supply constant and modulating extract or return keeps the qualified airflow and still holds the pressure cascade.
ISO 14644-1:2015 replaced the square-root rule for classification sampling locations with Table A.1. A 100 m² room went from 10 locations to 16. The revision also dropped the 95% UCL calculation and asks for one location per section of equal area. Requalification plans written before 2016 should be checked against the table.
5,500 CFM at 250 Pa is about 9,345 m³/h, 6.6% short of a 10,000 m³/h schedule at 400 Pa, and a 20 air-change room gets about 18.7. The static pressure gap shows only on the fan curve, and speeding the fan up for 7% more air costs about 23% more fan power.
For the same excess airflow, room pressure differential varies with the inverse square of the leakage area. On a finished cleanroom that area hides in door gaps, ungasketed light fittings, open socket boxes, panel joints and penetrations. Compare measured excess air with the design allowance at commissioning.
A 7.5 kW fan shaft load running 8,760 hours a year draws about 0.27 kW more at 90% motor efficiency than at 93%, roughly 2,350 kWh a year from one motor. Ask for tested motor-plus-drive efficiency at the duty point, because the IE class is rated at full load.
Voltage distortion is harmonic current multiplied by source impedance. An EC fan wall draws the same harmonic current on grid or generator, but a transformer is typically 4–6% impedance and a generator's subtransient reactance typically 12–20%. Model both sources and set a distortion limit for the busbar on standby power.
A passive LC filter is tuned to one harmonic order and adds leading kvar at light load. An active filter injects the opposite current, is sized in amps and follows the load. Cleanroom fan walls run at part speed most of the day, which favours the active filter.
Shrinking a 10,000 m³/h duct from 700 × 500 mm to 600 × 400 mm raises velocity from about 8 to 12 m/s and velocity pressure from 38 to 80 Pa, so every fitting costs about twice. Set separate limits for mains and branches in the design basis.
A recovery test with a 20-minute limit, traced to a 15-minute URS requirement, passes and leaves the requirement unproven. Reading a trace matrix from each test back to its requirement finds these weak links and orphan tests. Pick three signed results at random and trace them back.
A 10,000 m³/h fan at 1,500 Pa and 0.6 overall efficiency draws about 6.9 kW, around 61 MWh a year in a cleanroom. Every 100 Pa removed at design stage saves about 0.46 kW for the life of the plant. A pressure budget per AHU in the design basis is where it starts.
Air in a ceiling void has never passed a HEPA filter. If the void sits above room pressure, leaks bring it down past light frames and HEPA collars. Keep one void at or below the lowest room under it, seal duct joints, and measure room-to-void pressure at commissioning.
A 3 m cleanroom at 100 W/m² and an 8 K supply difference needs about 12 ACH for cooling. If cleanliness sets 40 ACH, the other 28 are dilution air. Moving it through the central AHU costs fan energy; a recirculation loop or FFUs can move it at lower pressure.