Air leaving a cooling coil stops short of the apparatus dew point by the bypass factor. With a 7 °C ADP, a bypass factor of 0.1 and 26 °C, 12 g/kg entering air, the leaving dew point is near 8.3 °C. Size the coil backwards from the dew point the supply air needs.
Long-lead AHUs are often ordered before a single end-of-design DQ report is signed, so a casing leakage class of L2 against a URS that asked for L1 surfaces at IQ as a deviation. Splitting DQ along the procurement packages, with each section signed before its order is released, finds it while the order can still change.
After a cold spell in northern Viet Nam, warm humid air arrives while floors and stored goods are still cold. Air at 20 °C and 90% RH has a dew point of about 18.3 °C, so a 15 °C slab gets wet. Extra ventilation adds more of the same air; dry the air or warm the surface.
With the motor in the airstream, fan power becomes heat: about 2.1 K at 1,500 Pa and 60% efficiency, roughly 14 kW on a 20,000 m³/h unit. After the coil it reaches the room; counted twice, it oversizes a chilled-water coil that then dehumidifies poorly at part load.
A recovery test with a 20-minute limit, traced to a 15-minute URS requirement, passes and leaves the requirement unproven. Reading a trace matrix from each test back to its requirement finds these weak links and orphan tests. Pick three signed results at random and trace them back.
A 10,000 m³/h fan at 1,500 Pa and 0.6 overall efficiency draws about 6.9 kW, around 61 MWh a year in a cleanroom. Every 100 Pa removed at design stage saves about 0.46 kW for the life of the plant. A pressure budget per AHU in the design basis is where it starts.
ASHRAE Guideline 14 treats a model as calibrated to monthly data when NMBE is within ±5% and CV(RMSE) within 15%. Before a model justifies a retrofit in a running plant, it should meet that bar against 12 months of metered data, including the wet season.
ASHRAE 0.4%, 1% and 2% design conditions are exceeded about 35, 88 and 175 hours a year. For a room with a validated RH limit, choosing the percentile is choosing how many excursion hours you accept. Use the dehumidification dew point column, choose per room, and write the choice into the design basis.
A 3 m cleanroom at 100 W/m² and an 8 K supply difference needs about 12 ACH for cooling. If cleanliness sets 40 ACH, the other 28 are dilution air. Moving it through the central AHU costs fan energy; a recirculation loop or FFUs can move it at lower pressure.
Cooling coils pay for dehumidification in chiller kWh; desiccant rotors mostly in reactivation heat, often above 100 °C for silica gel rotors. Compare them by listing the heat the site already has and its temperature. Very low dew points need desiccant regardless, and rotor outlet air still needs cooling.
Humiley engineers have a web-based AHU selection platform with one psychrometric engine and an ErP compliance module, so a junior and a lead get the same coil from the same design point. Reviews can then question the inputs: the governing design condition, latent load, fresh-air fraction and the RH limit.
Water needs about 2,450 kJ/kg to evaporate, so every kg/h leaving a mopped floor or wash bay adds about 0.68 kW of latent load. It arrives after production, when the cooling coil unloads. Treat the cleaning shift as its own dehumidification design case.