GAMP 5 software categories are 1, 3, 4 and 5; firmware stopped being Category 2 in 2008. Validation effort rises with each step, and a configured Category 4 SCADA can still hold Category 5 scripts that need custom-code testing. The 2022 Second Edition kept the categories.
Requalification and calibration usually run on separate schedules with separate owners. Put them on one calendar: calibrate room sensors before requalifying, check test instrument certificates at pre-test approval, and assess the impact on every result when a sensor fails calibration.
A spreadsheet that calculates F0, an assay result or an airflow figure is a computerized system under EU GMP Annex 11 once its answer drives a GMP decision. Locked formula cells, one released template under version control and formulas checked once by hand are the minimum an auditor will look for.
ISO 14644-1:2015 replaced the square-root rule for classification sampling locations with Table A.1. A 100 m² room went from 10 locations to 16. The revision also dropped the 95% UCL calculation and asks for one location per section of equal area. Requalification plans written before 2016 should be checked against the table.
Cleanroom inspectors ask for the same HVAC evidence: qualification report, pressure trends and alarm log, HEPA leak tests, classification and recovery, smoke studies, as-builts and change controls. Index them per room, with document number, revision and location, so the back room answers in minutes.
Where a SCADA, BMS or EMS records GMP-relevant data, access control, clock synchronization, alarm records and audit trails are decided by the electrical and automation engineers. Many sites keep those parameters on a separate validated EMS. Humiley's cross-functional training covers GMP, validation and project management.
Annex 1 sets zero growth as the APS target, and any contaminated unit fails it. The environmental side of the investigation starts from viable monitoring, with HVAC and EMS trends as support, so review trends before the fill, confirm logging and clock sync, and agree which HVAC events count as interruptions.
EU GMP Annex 11 clause 3.2 makes supplier competence and reliability part of computerized system validation, with the need for an audit set by risk. For SCADA, BMS and EMS, supplier records can reduce the testing the user repeats; the URS, risk assessment and configuration tests such as alarm limits and user roles stay with the user.
EU GMP Chapter 4 expects logbooks for major or critical equipment, recording use, calibration, maintenance, cleaning and repairs with dates and names. For an AHU serving graded rooms that means qualification events, sensor calibration, filter changes with differential pressure, repairs with deviation numbers and cleaning records.
A room's pressure differential sits on the room data sheet as a design value and in the monitoring SOP as alarm limits, often written months apart. Before OQ, list every door with the RDS revision it was balanced to and the current SOP alarm limits, and close each row that disagrees.
In an FMEA risk register, severity 10, occurrence 2 and detection 3 score an RPN of 60, below a nuisance risk at 100. Add a rule that any severity 9 or 10 comes to the weekly review whatever its RPN, and re-rate every risk after its mitigation.
EU GMP Chapter 4 asks that any alteration is signed and dated, leaves the original readable and records a reason where appropriate. Correction fluid, overwritten digits and blacked-out entries all break that rule and ALCOA+. Engineering and site teams need it in their induction as much as QA.