Split the handover by use. As-built CAD or BIM, the asset register, PLC and BMS source and the control narrative come in native, editable form. Signed protocols and certificates come as searchable PDF. One index by system and tag joins them, and the formats go into the contract before the first document.
AHUs bought in several tenders arrive with many motor frames, belt sections and filter sizes, and the spares list grows to match. A standardization schedule in the AHU datasheets before tender, covering IEC motor frames, standard filter faces, one sensor make and common belts, keeps the store small and repairs fast.
Ducted terminal HEPA and FFU ceilings can both reach Grade B or C. A ducted system sets airflow at one AHU fan; an FFU ceiling has many settings to hold, but a single failure stays local. Energy depends on fan efficiency and duct losses, so calculate it for the layout.
A filter passing 5% of particles with 2% of the air slipping round its frame passes almost 7%. EN 1886 measures that bypass on the AHU casing, and class F9 allows 0.5%. Frames, gaskets, clamps and rails decide the result, so put the class on the data sheet and check it at FAT.
Before the supply fan is selected, check whether the coil sheet quotes a wet or a dry air pressure drop, and read it with the entering condition: dry- and wet-bulb at the peak dew point case. Then check leaving dew point against room RH, face velocity below about 2.5 m/s and a realistic chilled-water ΔT.
A decontamination room can read negative on the BMS while its return air mixes with the packing room's in a shared ceiling void. ASHRAE 170 expects the room negative, at least 6 air changes per hour and all air exhausted outdoors. That needs an exhaust ducted all the way outside and a working washer-disinfector door interlock.
A hygienic AHU that passes FAT clean can still reach start-up full of site dust and condensation. Factory-fitted caps, wrapping that sheds rain without trapping moisture, desiccant for shipping, dry covered storage and an internal inspection before the first fan run protect what the FAT proved.
Airflow and kW alone leave a fresh-air coil's leaving dew point to the vendor's software. A comparable coil line adds entering dry and wet bulb at the wet-season design case, leaving dry bulb and dew point, chilled water temperatures, maximum face velocity and maximum air-side pressure drop.
5,500 CFM at 250 Pa is about 9,345 m³/h, 6.6% short of a 10,000 m³/h schedule at 400 Pa, and a 20 air-change room gets about 18.7. The static pressure gap shows only on the fan curve, and speeding the fan up for 7% more air costs about 23% more fan power.
ISO 16890 rates filters as ePM10, ePM2.5 or ePM1, and broadly a filter must remove at least 50% of that particle fraction to earn the group. In a GMP air handling unit the pre-filter grade sets how fast the terminal HEPA loads, and so how often it is replaced and leak-tested.
Drying 10,000 m³/h of wet-season air from a 26 °C to a 9 °C dew point removes about 170 kg of water an hour, roughly 4 m³ a day at full load. The condensate is low in minerals and a candidate for reuse such as cooling tower make-up, after a site assessment.
Before detail design opens, a GMP project should have frozen room data sheets and pressure cascade, loads that match the equipment list, a URS for each critical system and owned open items. A cascade change after the ducts are drawn reaches the duct sizes, terminal filters, AHU selection and every neighbouring pressure step.