Liquid-cooled battery racks move most heat outside, so the enclosure unit looks small on paper. But 18 °C coolant pipes sit inside, and on a wet afternoon outdoor air near 26 °C dew point comes in with every maintenance door opening. Specify an enclosure dew point limit below the coldest pipe.
Ho Chi Minh City outdoor air carries about 16 g/kg of water on the hottest afternoon and about 21 g/kg at peak dew point. A fresh-air coil sized on the hot condition falls short in the wet season, and after tender the fix is a variation. Settle it while the design is still moving.
Every 1,000 m³/h of outdoor air at 20 g/kg brings about 24 kg/h of water into a dry room plant, and the make-up airflow is set by process exhaust. A line exhausting 5,000 m³/h means about 120 kg/h. Firm exhaust flows come first.
Compressed air and nitrogen that drive product pigs, blanket vessels or purge tube fillers touch the product. Give each use point its own ISO 8573-1 class for particles, water and oil, sample after the final filter rather than at the compressor, and test viable counts to ISO 8573-7.
In a tropical plant the wet zone of a fresh-air AHU runs from the cooling coil and drain pan to the reheat coil. Specify stainless there, 316 where chlorine agents are used. Fan, pre-filter and mixing sections can be coated galvanised if cut edges are sealed. Ask for weld and passivation records.
ASHRAE 0.4%, 1% and 2% design conditions are exceeded about 35, 88 and 175 hours a year. For a room with a validated RH limit, choosing the percentile is choosing how many excursion hours you accept. Use the dehumidification dew point column, choose per room, and write the choice into the design basis.
A liquids suite is washed down often, so its contamination points are floor drains, floor falls, floor-wall joints and purified water outlets. Falls must reach the drain without ponding, drains must be cleanable, joints coved, outlets drainable and sampled, and airflow sized to dry the room before the next shift.
A dry room is a moisture mass balance. Air at a 25 °C dew point holds about 250 times the water of air at −40 °C, so makeup air usually dominates. People at about 80 g/h each, door events that drop the pressure, vapour permeation and materials carried in each need their own line.
Tropical GMP HVAC cools to dehumidify and then reheats, all year. A heat recovery chiller sends condenser heat to the reheat coils: 1,000 kW of cooling at COP 5 rejects about 1,200 kW. Condensing at 50 °C instead of 37 °C cuts ideal COP by about 30%, so it suits steady reheat.
Primary-secondary pumping is simple to control, but reverse flow in the decoupler sends warmer water to the coil that sets room dew point. Variable-primary saves pump energy but has to hold each chiller's minimum flow while chillers stage. For a GMP plant, choose the scheme your controls contractor can commission and prove.
Cooling coils pay for dehumidification in chiller kWh; desiccant rotors mostly in reactivation heat, often above 100 °C for silica gel rotors. Compare them by listing the heat the site already has and its temperature. Very low dew points need desiccant regardless, and rotor outlet air still needs cooling.
Humiley engineers have a web-based AHU selection platform with one psychrometric engine and an ErP compliance module, so a junior and a lead get the same coil from the same design point. Reviews can then question the inputs: the governing design condition, latent load, fresh-air fraction and the RH limit.